Quarter | |||||
1 | 2 | 3 | 4 | Year | |
Units | 20,340 | 25,110 | 35,440 | 30,500 | |
Direct Labor time per unit | 1.70 | 1.70 | 1.70 | 1.70 | |
Total Direct labor hours required | 34,578 | 42,687 | 60,248 | 51,850 | |
Wage rate | 15 | 15 | 17 | 17 | |
Direct Labor Cost | 518,670 | 640,305 | 1,024,216 | 881,450 | 3,064,641 |
Note:
Total Direct labor hours required = Units * Direct Labor required per unit
Direct Labor Cost = Total Direct labor hours required* Wage rate
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year Quarter Units Quarter Units 35,450 30,110 20,480 25,450 Each unit requires 1.70 hours of direct labor Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor Budget...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units 20,330 25,370 Quarter Units 3 35,270 4 30,390 oport 2 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Exercise 22-09 Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter arter Units Quarter 20,4803 25,450 Units 35,450 30,110 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC....
Exercise 21-9 Rodriguez, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 20,480 25,450 35,450 30,110 2 4 Each unit requires 1.70 hours of direct labor Prepare a direct labor budget for 2017. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units 20,360 25,210 Quarter 3 Units 35,460 30,430 Each unit requires 1.60 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor...
Exercise 9-9 (Video) Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year Quarter Quarter Units 20,270 25.380 Units 35,130 30,140 Each unit requires 1.30 hours of direct labor Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and 519 for quarters 3 and 4. (Round Direct labo 52.50.) RODRIQUEZ, INC. Direct Labor Budget Quarter
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,220 3 35,100 2 25,370 4 30,310 Each unit requires 1.80 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4
Exercise 22-09 (Video) Pharoah, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter Units 20,380 35,220 25,110 30,210 Each unit requires 1.60 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) PHAROAH, INC....
Your answer is partially correct. Try again. Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter 20,4403 25,3204 Units 35,320 30,380 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Dire RODRIQUEZ, INC. Direct Labor Budget For the Year Ending...
Marigold, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,110 3 35,370 2 25,410 4 30,440 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $18 for the first 2 quarters and $20 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.65.) MARIGOLD,...