Answer: 16 days
Explanation:
Activity - Duration
a - 2
b - 3
c - 5
d - 2
e -1
f - 7
Now we have 3 paths, first we need to calculate the total duration of each path.
Path 1) a -b - f
Total Duration = Duration of Activity A + Duration of Activity B + Duration of Activity F = 2 + 3 + 7 = 12 days
Path 2) a - c -d -f
Total Duration = Duration of Activity A + Duration of Activity C + Duration of Activity D + Duration of Activity F = 2 + 5 + 2 + 7 = 16 days
Path 3) a-c-e-f
Total Duration = Duration of Activity A +Duration of Activity C + Duration of Activity E + Duration of Activity F = 2 + 5 + 1 + 7 = 15 days
Total Duration of Path 2 is the longest one so Path 2 is a critical path.
Days Required to complete the project = Total Duration of Critical Path (Path 2) = 16 days
Question 1 A project has 6 activities a, b, c, d, e and f. Their estimated...
A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...
The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job Predecessor mi expected variance number Job(s) time (ET) --- 468 B A 3 4 5 CIA 234|| D C 34 11 E B, C 13 5 D, E 2 46 F b. [Sketch the network diagram for the project on a...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
Concerning the activities the following standards were set: ACTIVITY DESCRIPTION PRECEDING ACTIVITY ACTIVITY DURATION(DAYS) A Feasibility Study None 7 B Internal Specs A 5 C External Specs A 13 D Internal Analysis B 5 E Functional Specs C,D 10 F Hardware Specs E 15 G Hardware Acquisition F 5 H System Installation G 3 I Design material A 45 J System Testing H,I 10 a) Draw a network diagram (Activity-on-None) of the project presented in the case study with all...