Question

The following table represents the set of activities required to complete a project, along with their time estimates for PERT

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a:

Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2
A 4 6 8 6.00 0.44
B 3 4 5 4.00 0.11
C 2 3 4 3.00 0.11
D 3 4 11 5.00 1.78
E 1 3 5 3.00 0.44
F 2 4 6 4.00 0.44

Answer b:

Answer c:

Paths Duration
ABEF 17.00 Longest path
ACEF 16.00
ACDF 16.00

Answer d: Critical path is ABEF. The expected completion time of the project is 17 days.

Add a comment
Know the answer?
Add Answer to:
The following table represents the set of activities required to complete a project, along with their...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT