Question

Benson Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows Direct labor Direct materials $71,000 $ 98,000 $171,000 91,000 148,000 183,000 Assume Benson needs to allocate two major overhead costs ($34,000 of employee fringe benefits and $29,540 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overheed costs and determine the total cost of each house. (Round Allocation rate to 2 decimal places.) Fringe Benefits: Total
media%2F11d%2F11d137c0-2a46-44c4-83a3-c3
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Allocation rate:
Fringe Benefits (basaed on direct labour): Total Fringe benefits cost/ Direct labour cost *100
$ 34000 /340000 *100 = 10% of Labour cost
Indirect Material (based on indirect material): Indirect material cost/ Direct Material cost *100
$ 29540 / 422,000 *100 = 7% of Material cost
Fringe benefits
Home Allocation rate Weights of Base = Allocated cost
1 10% 71000 7100
2 10% 98000 9800
3 10% 171000 17100
Total 34000
Indirect Material
Home Allocation rate Weights of Base = Allocated cost
1 7% 91000 6370
2 7% 148000 10360
3 7% 183000 12810
Total 29540
Expected Cost
Home 1 Home 2 Home 3
Direct Labour 71000 98000 171000
Direct Material 91000 148000 183000
Fringe benefits 7100 9800 17100
Indirect material 6370 10360 12810
Total cost 175470 266160 383910
Add a comment
Know the answer?
Add Answer to:
Benson Construction Company expects to build three new homes during a specific accounting period. The estimated...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Benson Construction Company expects to build three new homes during a specific accounting period. The estimated direct...

    Benson Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows: Expected Costs Direct labor Home 3 Home 1 Home 2 $ 69, e00 $1өө, өөө $186,өөө Direct 131,000 103,000 180,000 materials Assume Benson needs to allocate two major overhead costs ($53,250 of employee fringe benefits and $33,120 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead...

  • Fanning Construction Company expects to build three new homes during a specific accounting period. The estimated...

    Fanning Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows: Expected Costs Home 1 Home 2 Home 3 Direct labor $ 80,000 $ 98,000 $ 186,000 Direct materials 102,000 132,000 180,000 Assume Fanning needs to allocate two major overhead costs ($54,600 of employee fringe benefits and $28,980 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead...

  • Thornton Construction Company expects to build three new homes during a specific accounting period. The estimated...

    Thornton Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Costa Direct labor Direct materials Home 1 $ 65,000 99,000 Home 2 $ 108,000 147,000 Home 3 $173,000 191,000 Assume Thornton needs to allocate two major overhead costs ($51,900 of employee fringe benefits and $30,590 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead costs...

  • Thornton Construction Company expects to build three new homes during a specific accounting period. The estimated...

    Thornton Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Costa Direct labor Direct materials Home 1 $ 65,000 99,000 Home 2 $ 108,000 147,000 Home 3 $173,000 191,000 Assume Thornton needs to allocate two major overhead costs ($51,900 of employee fringe benefits and $30,590 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead costs...

  • Zachary Construction Company expects to build three new homes during a specific accounting period. The estimated direct...

    Zachary Construction Company expects to build three new homes during a specific accounting period. The estimated direct materia and labor costs are as follows: Expected costs Direct labor Direct materials Home 1 $ 68,000 103,000 Home 2 $ 97,000 135,000 Home 3 $184,000 197,000 Assume Zachary needs to allocate two major overhead costs ($69,800 of employee fringe benefits and $30,450 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead costs...

  • Zachary Construction Company expects to build three new homes during a specific accounting period. The estimated...

    Zachary Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Costs Direct labor Direct materials Home 1 $ 73,000 100,000 Home 2 $ 105,000 139,000 Home 3 $ 190,000 184,000 Assume Zachary needs to allocate two major overhead costs ($73,600 of employee fringe benefits and $8,460 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead...

  • Campbell Construction Company expects to build three new homes during a specific accounting period. The estimated...

    Campbell Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Costs Direct labor Direct materials Home 1 $ 74,000 108,000 Home 2 $ 92,000 147,000 Home 3 $186,000 182,000 Assume Campbell needs to allocate two major overhead costs ($35,200 of employee fringe benefits and $21,850 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the overhead costs...

  • Fanya Construction Company expects to build three new homes during a specific accounting period and labor...

    Fanya Construction Company expects to build three new homes during a specific accounting period and labor costs are as follows: direct materials Expected Costs Direct labor Direct materials Home 1 $40,000 30,000 Home 2 11 Home 3 $60,000 $100.000 50,000 80.000 points (8 01:45:09 Assume Fanya needs to allocate two major overhead costs ($80,000 of employee fringe ployee fringe benefits and $40,000 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the...

  • Exercise 12-8 Allocating costs among products LO 12-3 Jordan Construction Company expects to build three new...

    Exercise 12-8 Allocating costs among products LO 12-3 Jordan Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows: Expected Costs Direct labor Direct materials Home 1 $79,000 93.000 Home 2 $ 93,000 134,000 Home 3 $182,000 191,000 Assume Jordan needs to allocate two major overhead costs ($53,100 of employee fringe benefits and $20,900 of indirect materials costs) among the three jobs. Required Choose an appropriate cost...

  • Home 3 Total The cost components to determine the total cost of each house: Expected Costs...

    Home 3 Total The cost components to determine the total cost of each house: Expected Costs Home 1 Home 2 Direct labor Direct materials Fringe benefits Indirect materials Total cost 0 $ $ 0 $ 0 Jordan Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Costs Direct labor Direct materials Home 1 $ 62,000 98,000 Home 2 $ 95,000 138,000 Home 3 $187,000 191,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT