Question

St. Francis Assisted Living Facility St. Francis Medical Center, a 450 bed rehabilitation non-profit hospital began...

St. Francis Assisted Living Facility St. Francis Medical Center, a 450 bed rehabilitation non-profit hospital began to see a significant decline in admissions. St. Francis' mission focuses on inpatient and outpatient rehabilitation of the severely injured and catastrophically ill. While the patient census varied from month to month, it appeared to the St. Francis Board of Trustees that the inpatient population was slowly but steadily declining. The hospital's market researchers reported that fewer people were being severely injured due to the popularity of seat belts and bicycle/motorcycle helmets. In order to get a handle on the future of the organization, the Board, and the CEO, Sandra Kline M.D. called for a major strategic planning effort to take place.

In January 2018, St. Francis held a planning retreat to identify future opportunities. The outcome of the retreat was that the Medical Center needed to focus its efforts around two major strategic initiatives. The first, a short run initiative, was to be more cost effective in the delivery of inpatient care. The second, a long-run strategy, was to develop new programs and services that would capitalize on the existing, highly competent rehabilitation therapy staff and St. Francis's excellent reputation in the region.

At the time of the retreat, Sandra Kline's parents were living with her family. Her parents were aging and developing many problems common to the elderly population. Their medical needs were increasing and it crossed Sandra's mind that the hospital Board might consider to expand the Medical Center's campus to include an assisted living facility.

In March 2018, Sandra had her Business Development team prepare a rough estimate of the potential return on investment of an assisted living facility. She asked the team to identify different options for facility construction and the associated costs. The team also did a complete competitive analysis and examined the options for services to be offered based on St. Francis's potential population base within the local area. The Business Development team visited several facilities across the country. The team also interviewed companies that could oversee the design, building, and operation of the facility for St. Francis. The development team produced a preliminary business plan based on the recommended structure for the facility, estimated capital expenditure needs, estimated income from operation of the facility, as well as projected revenues to other Medical Center programs resulting from the facility's population.

The plan was presented at the May 2018 meeting of the Board of Trustees. Sandra Kline and her team introduced the Board to the concept of opening an assisted living facility on St. Francis's campus. The facility would be set up as a for-profit subsidiary of the Medical Center so that it could generate a profit and not be subjected to the strict guidelines of the hospital's accrediting agencies. As a subsidiary organization, however, the Board would still have control.

The chosen facility design would be an apartment-like facility with a sheltered connection to the Hospital for access to the kitchen and hospital services. The facility would have 200 units with 25 to 50 of the units classified as “heavy-assisted”; built to house the physically and medically disabled. The rest of the units would be “light-assisted,” larger apartments. The population would be approximately 220 to 300 residents, serving both single occupants and couples.

The light-assisted apartments could hold residents who required only minor medical and social interventions. The residents of the heavy-assisted section would have more medical needs and would require assistance getting around. The Business Development team recommended this type of programming model, because many assisted living facilities were erected across the country, but few had a medical focus and offered the types of services that St. Francis could offer—physical and occupational therapy programs, and behavior management programs to name a few.

The Board was assured that the facility would meet the strategic initiative of a growing business. The business plan projected an immediate increase in the number of referrals to the outpatient therapy programs. Another projected deliverable of the project was to enable St. Francis to strengthen its focus on reimbursable preventive and wellness programs for the healthier elderly population. The project's longer term goal was to increase the census in the hospital's inpatient units by having a location where people could age in place until they were in need of hospitalization, and then such a facility would be right next door.

Depending on the exact size of the apartments, their equipment, and the actual ratio of heavy-to light-assisted units, Sandra estimated that the entire project would cost between $9,000,000 and $12,000,000 for the facility construction. That estimate included the cost of land, furnishings, and a sheltered connection to the hospital. When up and running, it was estimated that the net income would range between $14,400 and $18,000 per unit per year. The team estimated the net cash flow for the entire project to be around $2,000,000 per year.

Sandra requested the Board to approve the concept and allow her team to proceed with the initiative. The project would include designing/constructing both heavy and light assisted-living apartments. It would include costs of land, construction, furnishings, staffing, and operations (patient services).

The Board conducted several executive sessions, and by the middle of May, after approval, a charter was drafted. The architectural-construction-management firm recommended by the team was approved. The Board appointed two Board members to sit on the planning group.

In June, Dr. Kline gathered her executive team together and presented the project mission, and scope. She reported that the board had approved a small budget to finance the planning process. The Board also stipulated that construction could not begin until after the November 2018 city elections because two of the Board Members were running in that election, one for a city council seat and one as a county commissioner. The Board also stated that they would like a plan that would allow the facility to open by July 2020, as research has shown that many adult children find the summer the easiest time to assist their parents in finding an alternative to independent living arrangements. The CEO and executive team were now confident that they were ready to launch the project to plan, build, and open an assisted living facility at St. Francis.

A few days later, Sandra decided that it was time to set up the team that would take Responsibility for what she called the CALF (Construction – Assisted Living Facility) project. She included the following staff at the launch meeting:

Chief Financial Officer (CFO)

Vice President of Business Development and Marketing

Rehab Services Medical Director

Construction Project Manager for capital facilities projects

Chief Operations Officer (COO) (nursing, facilities, food services, and housekeeping)

Director of Information Services

Director of Support Services (central supply, purchasing, and security)

Two members of the Board of Trustees, one with construction experience and the other a probable electee to the city council.

Even though the department directors from Support Services and Information Services would not be involved until later, Sandra decided to include them from the beginning. Sandra knew some members had a tendency to become obstacles to progress if they felt left out.

Sandra named the group the CALF Project Steering Committee and held the first meeting. Sandra presented her vision for the facility. She told the group that she personally would be managing this project. She led a discussion of all the major steps that must be included in the project plan, and asked each team member to identify the areas for which they would accept responsibility. The hospital's Construction Project Manager took responsibility for the construction of the facility, and the COO volunteered to oversee the building design, as well as define the needs for food services, housekeeping, staffing, and policy and procedure development. The CFO agreed to develop the budgets for each area of the project as well as the operating budget for the facility. The CFO also agreed to create the payroll and accounting systems necessary to operate the facility.

The IS director accepted responsibility to define and set up all the telecommunications and information system needs of the facility. The VP of Business Development agreed to create a preliminary marketing plan, and a communication package for the community and hospital staff. In addition, she discussed organizing a major ground breaking event.

The Medical Director said that he would design an assessment tool for determining residents' level of medical needs upon moving in to the facility. He felt this was the first step in defining what clinical services should be offered to residents. Sandra told the team that she would develop the management structure for the new facility and work with in-house counsel to identify all governmental regulations as well as all industry standards that pertain to an assisted living facility and govern the facility's practices. Sandra gave the team two months to come back with their detailed action plans for their areas of responsibility.

Deliverable #1:
Assume that two months have lapsed. Based on the feedback from executive members, your team will assist Sandra in creating a preliminary WBS. Use the attached template to assist with the process. Be mindful that the template shows four different formats to display the WBS; the outline view, the hierarchical structure, the tabular view and the tree structure view. You only need to select one of those views to complete the assignment. It is recommended that you consider using Project software (i.e. MS Project) to complete the assignment. The expectation is that much of the work contained on the WBS will be decomposed to level 3 (at a minimum).  

Deliverable #2:
Choose ONLY "ONE" work package and create an accompanying WBS Dictionary. Remember a WP is the lowest level on a WBS. Use the information provided in the case to define estimates associated with the chosen work package. You may NOT be able to fill in all the information. As with many of the project documents, this document evolves through progressive elaboration as the project progresses. Some of the data will be filled in at later stages. Do your best to fill in all the information you can at this stage in the process.

Notes:
There is no perfect WBS. Keep your levels correct. Use the information discussed in the case and classify accordingly. Once the main categories are defined, decompose, or breakdown, to lower levels. Your last component, or last breakdown, is always called the work package, regardless of the level in which it is located. This is the box that would be defined in the WBS Dictionary for additional details.

Deliverable #3:

As a group, discuss and provide your rationale (~1 page) associated with the following question: Is Dr. Kline a good choice for the project manager. Why/Why not?

1 0
Add a comment Improve this question Transcribed image text
Answer #1

a. Here, I would like to use an outline view to give an overall picture of the assignment.

1. Development of assisted living facility

1.1 Preparation of rough estimates

1.1.1 Identify options for facility construction

1.1.2 Complete competitive analysis

1.1.3 Prepare preliminary analysis and business plan

1.1.4 Develop an overall blueprint of the structure

1.2 Defining objectives and practical applications of the plan

1.2.1 Elucidate long term and short term goals.

1.2.2 Conducting a cost-benefit analysis

1.2.3 Preparing fair plan

1.2.4 Approval from the board

1.2.5 Hiring responsibility team members

1.3 Action plan

1.3.1 Discussion of major steps

1.3.2 Complying with legal formalities

1.3.3 Assigning responsibilities

1.3.4 Implementing the project

1.3.5 Periodic analysis of the sublimity of the plan.

b.   A work package is the most basic component of a WBS. I am selecting implementation stage(1.3.4) The terms given below are a part of the implementation.

NO TERM DEFINITION

1. Steering committee Committee formed to implement the program

2. Payroll Contains details of employees and their salary

3. Procedure development Developing steps to implement a project

4. Marketing plan A scheme to promote the idea

c. There is no doubt for the fact that Dr. Kline is an outstanding project manager. One of the important traits that a good project manager must require is to have a well-developed vision. Sandra Cline not only has a very good vision, but also good leadership skills, coordination and commanding ability. She also gives a chance to the team members to decide their own responsibilities. So, being an easygoing capable leader, she is a good choice for a project manager.

  

Add a comment
Know the answer?
Add Answer to:
St. Francis Assisted Living Facility St. Francis Medical Center, a 450 bed rehabilitation non-profit hospital began...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Friendly Assisted Living Facility-1 Friendly Medical Center, an urban, nonprofit, 450-bed rehabilitation hospital, began to see...

    Friendly Assisted Living Facility-1 Friendly Medical Center, an urban, nonprofit, 450-bed rehabilitation hospital, began to see a significant decline in admissions. Friendly Medical Center's mission focuses on inpatient and outpatient rehabilitation of the severely injured and catastrophically ill. While the patient census varied from month to month, it appeared to the Friendly Medical Center Board of Trustees that the inpatient popu- lation was slowly but steadily declining. The hospital's market researchers reported that fewer people were being severely injured due...

  • 1) bomar imorgan x > Project Management in Practice x + 532 Project Management in_Practice_6th_6bf4.pdf C...

    1) bomar imorgan x > Project Management in Practice x + 532 Project Management in_Practice_6th_6bf4.pdf C A SE Friendly Assisted Living Facility Project Budget Development-4 Fred Splient gave his ALF Project Steering Committee 2 months to develop a project plan for their area of respon sibility in the project. Each member was told to include the tasks predecessors and successors, resources needed, responsible person, and an estimated cost. He asked that these be presented to the steering team on August...

  • plz answer the questions at the bottom 1) bomar imorgan x > Project Management in Practice...

    plz answer the questions at the bottom 1) bomar imorgan x > Project Management in Practice x + 532 Project Management in_Practice_6th_6bf4.pdf C A SE Friendly Assisted Living Facility Project Budget Development-4 Fred Splient gave his ALF Project Steering Committee 2 months to develop a project plan for their area of respon sibility in the project. Each member was told to include the tasks predecessors and successors, resources needed, responsible person, and an estimated cost. He asked that these be...

  • A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of external affairs for a national not-for-profit medical research center that does resea...

    A Not-for-Profit Medical Research Center A Not-for-Profit Medical Research Center You are Alexis, the director of external affairs for a national not-for-profit medical research center that does research on diseases related to aging. The center’s work depends on funding from multiple sources, including the general public, individual estates, and grants from corporations, foundations, and the federal government. Your department prepares an annual report of the center’s accomplishments and financial status for the board of directors. It is mostly text with...

  • 1.D Multiple-Choice Exercises 1. The most expensive type of healthcare setting is usually a(n) a) assisted-living...

    1.D Multiple-Choice Exercises 1. The most expensive type of healthcare setting is usually a(n) a) assisted-living community. b) hospice organization. c) respite care facility. acute care facility. 2. OBRA is federal legislation that regulates rehabilitation hospitals. b) long-term care facilities. c) respite care services. d) home health agencies. 3. To ensure that hospitals are in compliance with federal regulations, they are surveyed by the a) Joint Commission at least every year. b) Joint Commission at least once every 3 years....

  • Entering and Contracting Contracting at Charity Medical Center Charity Medical Center (CMC), a five hundred-bed acute-care...

    Entering and Contracting Contracting at Charity Medical Center Charity Medical Center (CMC), a five hundred-bed acute-care hospital, was part of the Jefferson Hospital Corporation (JHC). JHC, which operated several long-term and acute-care facilities and was sponsored by a large religious organization, had recently been formed and was trying to establish accounting and finance, materials management, and human resources systems to manage and coordinate the different facilities of particular concern to CMC, however, was a market share that had been declining...

  • #2 Please FLEXIBLE BENEFITS SYSTEM IMPLEMENTATION AT MEDICAL CENTER CASE 1.2 ement a ne Senior management...

    #2 Please FLEXIBLE BENEFITS SYSTEM IMPLEMENTATION AT MEDICAL CENTER CASE 1.2 ement a ne Senior management of Shah Alam Medical Center decided to system that would reduce the cost and improve the service of its emplo procure and implem yee benefits cover stem would have to meet four goals: improved responsiveness to employee nea s flexibility, better cost management, and greater coordination of human resoura re tives from four departments-Human Resources (HR). Financial Systems (FS), and Int Services (IS)-and six...

  • Sabrina Hoffman is founder and CEO of Golden Care, Inc., which owns and operates several assisted-living...

    Sabrina Hoffman is founder and CEO of Golden Care, Inc., which owns and operates several assisted-living facilities. The facilities are apartment-style buildings with 25 to 30 one- or two-bedroom apartments. While each apartment has its own complete kitchen, in every building Golden Care offers communal dining options and an on-site nurse who is available 24 hours a day. Residents can choose monthly meal options that include one or two meals per day in the dining room. Residents who require nursing...

  • Case 5 Twin Falls Community Hospital (Capital Investment Analysis) Twin Falls Community Hospital is a 250-bed,...

    Case 5 Twin Falls Community Hospital (Capital Investment Analysis) Twin Falls Community Hospital is a 250-bed, not-for-profit hospital located in the city of Twin Falls, the largest city in Idaho’s Magic Valley region and the seventh largest in the state. The hospital was founded in 1972 and today is acknowledged to be one of the leading healthcare providers in the area. Twin Falls’ management is currently evaluating a proposed ambulatory (outpatient) surgery center. Over 80 percent of all outpatient surgery...

  • Minutes from the Planning Committee Meeting Present: Ms. Morehouse, administrator; Mr. Hassan, finance and admissions coordinator;...

    Minutes from the Planning Committee Meeting Present: Ms. Morehouse, administrator; Mr. Hassan, finance and admissions coordinator; Mr. Washington, food services director; Ms. Laird, director of nursing; Ms. Smith, rehabilitation supervisor; Mr. Keith, construction representative; Mr. Morgan, designer; Mr. Welbourne, contractor; Ms. Reese, architect. The meeting started at 9 a.m. Ms. Morehouse began with introductions of those present. She 702 explained that culture change in the nursing home industry was going to gain momentum and, if traditional facilities did not adapt...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT