Answer
Work element | t | F | RF | t*F*RF | |
1 | 0.4 | 1 | 1 | 0.4 | =B2*C2*D2 |
2 | 0.32 | 0.5 | 0.8 | 0.128 | |
3 | 0.2 | 1 | 1.2 | 0.24 | |
4 | 0.5 | 1 | 1.3 | 0.65 | |
Normal time | 1.418 | SUM(E2:E5) | |||
Allownace factor | 20% | ||||
Standard time | = | Normal time (1 + Allowance factor) | |||
Standard time | = | =1.418*(1+20%) | |||
Standard time | = | 1.7016 |
Definition of Standard time - It is the time required by an operator to perform a specific task working at a standard pace.
If you liked my answer , thumbs up pls.
Question one: A job is divided into four work elements. Work element t F RF 1...
What is a Therblig? Please specify and give exampie. 3) A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Note that all units are in minutes 15 Element Performance 1 13 4 6 rating 85% 100% 110% 95% 0.5 258* 0.89 1.14 0.46 1.52 0.8 0.44 1.5 0.84 1.1 0.43 1.47 0.48 1.49 0.85 0.45 1.51 0.83 1.081.21.161.26 4 * Machine broke...
A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Element Performance Rating 1 2 3 4 5 6 1 80 % 0.51 0.56 0.46 0.46 0.46 0.46 2 75 1.51 1.51 1.46 1.46 1.46 1.51 3 120 0.86 0.86 0.76 0.81 0.86 0.81 4 105 1.11 1.16 1.11 1.16 1.16 1.21 a. Determine the average cycle time for...
the elements together with the predecessor and processing time of two models A and B are shown in table below. hourly production rate of model a and b are 25 units/hr and 18 units/hr. assume E=1.0, Er=1.0 and M=1. a) draw the precedence diagram for each model and both models b) find the theoretical number of workstation needed to achieve the required production rate. c) use K-W method to solve the line balancing problem d) determine the balance efficiency for...
4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...
PLEASE SOLVE 1 TO 4 PLEASE SHOW WORK. WILL UPVOTE WITHIN A DAY. Part A: In the small network below, there are four possible routes to go from A to B. Find the shortest path based on the impedance, as defined below: 1. Length 2. Travel time 3. Travel time with intersection penalties, where right turn adds 0.5 minutes, through movement adds 1 minute and left turn adds 1.5 minutes 4. Travel cost, where you should estimate a generalized cost...
please show work!! Additional Algo 14-3 Standard Deviation of Demand Over Multiple Periods Each period, demand for apples is normally distributed with a mean of 290 and standard deviation of 70 Round your answer to two decimal places. What is the standard deviation of demand over 2 periods? PA 14-5 A Cold Inc is a frozen food distributor with... Use Table 141 ACold Inc is a frozen food distributor with 10 warehouses across the country. Ivan Tory, one of the...
kindly assist: PROJECT 1: ORGANISATIONAL LEADERSHIP QUESTION 1 (60) In most organisations, people issues usually take up most of the management's time, since managers have to resolve problems relating to issues such as performance contracts, conflict between employees, motivating the workforce and keeping subordinates informed. 1.1 Discuss in detail, with the use of examples, FIVE (5) general traits or personality characteristics that individuals in a business, including managers', fall within. (20) 1.2 The individual's satisfaction with various aspects of his...
please answer all them, i have enough questions left! ? question #1 please :) Examples on Asset Pricing Models 25 (2-2)(RA) = 12.2%; EOR 1. You are given the following equilibrium expected returns and risks: 3.7 (RM-Red E(RA) = 12.2%; E(RB) = 15.5%; Ba=0.7; BB = 1.25. ER2=0.08 +0.06 Bi a. What is the equation of the Security Market Line? b. A portfolio, made up of A (above) and another security, has a beta of 1.10 and expected return of...
please answer question 4 Examples on Asset Pricing Models 1. You are given the following equilibrium expected returns and risks -07: 12 ke (RA) - 12.296; E(R) -15.556; No. 0. 015 a. What is the equation of the Security Market Line? b. A portfolio, made up of A (above) and another security, has a beta of 1.10 and expected return of 1396Which one would you rather buy - A alone or the portfolio? Why? ES 1.6 I OVAL B A...
A common practice of airline companies is to sell more tickets for a particular flight than there are seats on the plane, because customers who buy tickets do not always show up for the flight. Suppose that the percentage of no-shows at flight time is 2%. For a particular flight with 244 seats, a total of 250 tickets were sold. What is the probability that the airline overbooked this flight? Click here to view page 1 of the standard normal...