Initial Investment=1900000+140000=$2040000
Depreciation cost per year=1,900,000/5=$380000
Fixed Cost=$275000
Gross Profit per year=(17-10.4)*150000-275000=$715000
Taxable profit= Gross Profit- Depreciation=715000-380000=$335000
Tax=335000*25%=$83750
Cash flow=715000-83750=$631250
5th year cash flow including salvage value=631250+160000=$791250
Year | Cash Flow | Present Value (Cash Flow/1.12^year) |
- | (2,040,000) | (2,040,000) |
1 | 631,250 | 563,616 |
2 | 631,250 | 503,229 |
3 | 631,250 | 449,311 |
4 | 631,250 | 401,171 |
5 | 791,250 | 448,976 |
NPV (Total Present Value) | 326,303 |
a. Hence, NPV of the project is $326303
b. Say, x is the minimum number of cartons
Now, Gross Profit=x*(17-10.4)-275000
Profit After depreciation=x*(17-10.4)-275000-380000=0
now, 6.6x=655000
or, x=99242.42 or 99242 (Approx)
c. say, the highest fixed cost that can be undertaken is y
Then, (17-10.4)*150000-y-380000=0
or, y=(17-10.4)*150000-380000=610000
Hence, highest fixed cost that be incurred is $610000
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 145,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 154,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 150,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems Romo Enterprises needs someone to supply it with 124,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Martin Enterprises needs someone to supply it with 130,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Martin Enterprises needs someone to supply it with 126,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Martin Enterprises needs someone to supply it with 134,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Martin Enterprises needs someone to supply it with 126,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. 0.58 points eBook Martin Enterprises needs someone to supply it with 138,000 cartons of machine screws per year to support its manufacturing needs over the next five...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Martin Enterprises needs someone to supply it with 132,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've...