Question

A part structure and lead times (weeks) for product A are shown in the product structure. Click the icon to view the productA part structure and lead times (weeks) for product A are shown in the product structure. Click the icon to view the productThe product structure. LT=Lead time in weeks LT=1

0 0
Add a comment Improve this question Transcribed image text
Answer #1

C is a sub competent of B and B is a subcomponent of A. An increase in lead time of C directly impacts B & indirectly impacts A. Hence, answer is B and or A.

Since an increase in lead time of C causes an overall increase in lead time along chain of C-> B-> A. This can be compensated if lead time for B & or A can be reduced. For example : A reduced lead time by 0.5 weeks in B & A will have no impact on overall lead time

Add a comment
Know the answer?
Add Answer to:
A part structure and lead times (weeks) for product A are shown in the product structure....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT