Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans.
565 | ||
X43 | Y36(2) | N78 |
J27(4) X43 |
Part Number | On Hand | Lot Size | Lead Time |
565 | 0 | Lot-for-lot | 1 week |
X43 | 60 | Multiples of 120 | 1 week |
N78 | 0 | Lot-for-lot | 2 weeks |
Y36 | 200 | Lot-for-lot |
1 week |
J27 | 0 | Lot-for-lot | 2 weeks |
Master Schedule for: | Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
565 | Quantity | 180 |
565 | LT=1 wk | |||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross Requirement | 0 | 0 | 0 | 0 | 0 | 180 | 0 | 0 |
On Hand (0) | ||||||||
Net requirement | 0 | 0 | 0 | 0 | 0 | 180 | 0 | 0 |
Planned Order Receipt | 0 | 0 | 0 | 0 | 0 | 180 | 0 | 0 |
Planned Order Release | 0 | 0 | 0 | 0 | 180 | 0 | 0 | 0 |
For 1 565 2 units of Y(36) required and the Gross Requirement will be on the same period of planned order release of 565
Y36 | LT= 1wk | |||||||
Gross Requirement | 0 | 0 | 0 | 0 | 360 | 0 | 0 | 0 |
On Hand (200) | 200 | 200 | 200 | 200 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 0 | 160 | 0 | 0 | 0 |
Planned Order Receipt | 0 | 0 | 0 | 0 | 160 | 0 | 0 | 0 |
Planned Order Release | 0 | 0 | 0 | 160 | 0 | 0 | 0 | 0 |
One unit of N78 is required for 1 unit of 565
N78 | LT= 2 wks | |||||||
Gross Requirement | 0 | 0 | 0 | 0 | 180 | 0 | 0 | 0 |
On Hand (0) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 0 | 180 | 0 | 0 | 0 |
Planned Order Receipt | 0 | 0 | 0 | 0 | 180 | 0 | 0 | 0 |
Planned Order Release | 0 | 0 | 180 | 0 | 0 | 0 | 0 | 0 |
4 it's of J27 required for 1 unit of Y36
J27 | Lt= 2 wks | |||||||
Gross Requirement | 0 | 0 | 0 | 640 | 0 | 0 | 0 | 0 |
On Hand (0) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 640 | 0 | 0 | 0 | 0 |
Planned Order Receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Planned Order Release | 0 | 640 | 0 | 0 | 0 | 0 | 0 | 0 |
X43 | Lt= 1wk | |||||||
Gross Requirement | 0 | 0 | 0 | 160 | 180 | 0 | 0 | 0 |
On Hand (0) | 60 | 60 | 60 | 20 | 80 | 80 | 80 | 80 |
Net requirement | 0 | 0 | 0 | 100 | 160 | 0 | 0 | 0 |
Planned Order Receipt | 0 | 0 | 0 | 120 | 240 | 0 | 0 | 0 |
Planned Order Release | 0 | 0 | 120 | 240 | 0 | 0 | 0 | 0 |
Please rate me
thanks
Determine planned order releases for each part shown in the product structure tree. 180 units of...
Question #1 : The product structure tree of a round-top computer desk is given as follows. On-hand inventory information is given in the Table 1 as follows. Level 0 Round-top computer desk (A) Level 1 B(4) C(2) Level 2 E(2) F(3) E(3) D(2) D(1) D(3) Level 3 Table 1: On-hand inventory Item On hand (units) Round-top com r desk 100 48 20 1) Determine number of units of each item required to satisfy a new order of 10 round-top computer...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...
(20 points) The bill-of-materials tree for 5. Standard remote Deluxe remote two remotes are shown on the right Std keypad Back case Batteries (2) You need 100 standard remotes each in weeks 4 s Back case 1 Batteries (2) You need 150 deluxe remotes in week 5. A. Fill out the tables below to find the number of each item to order each week assuming lot-for-lot ordering Item: Standard remote Lead time week Gross requirements On hand 60 60 Net...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
Please provide equation for each box
4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 Asto be available in week 5. There are 20 Bs available. All other on-hand balances =0. B(2) B (1) D(1) (1) D(2) RI) Part Number Week 3 1 2 4 5 100 Part Number Quantity B 2 D...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...