Please give the correct answer and explanation, 10 weeks is incorrect.
The sequence of items from Finished product (A) upto last component in the product structure and the total lead time (LT) are listed below:
A-B-D, Total LT = 1+1+3 = 5
A-B-E-H, Total LT = 1+1+7+4 = 13
A-B-E-G, Total LT = 1+1+7+5 = 14
A-C-F, Total LT = 1+2+5 = 8
A-C-H, Total LT = 1+2+4 = 7
a)
Considering no existing inventory or scheduled receipts, the longest Total LT is 14 weeks. Therefore,
Lead time needed to respond to a customer order for product A = 14 weeks
b)
Considering sufficient inventory of items D,F,G,H , the response time of these items is 0.
A-B-D, Total LT = 1+1+0 = 2
A-B-E-H, Total LT = 1+1+7+0 = 9
A-B-E-G, Total LT = 1+1+7+0 = 9
A-C-F, Total LT = 1+2+0 = 3
A-C-H, Total LT = 1+2+0 = 3
Therefore, Customer response time = 9 weeks
Please give the correct answer and explanation, 10 weeks is incorrect. Product A is made from...
Product A is made from components B and C. Item B, in turn, is made from D and E. Item C also is an intermediate item, made from F and H. Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead times: A B D Item Lead Time (weeks) a. What lead time (in weeks) inventories or scheduled receipts?weeks. (Enter your response as an integer.) 4 2 5...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 100 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below Item Data Category L4L 2 weeks 100 (week 2) 350 L4L 1 week None 215 Lot-sizing rule Lead time Scheduled receipts Beginning inventory...
A part structure and lead times (weeks) for product A are shown in the product structure. Click the icon to view the product structure. This exercise contains only parts a and c. You have just been notified via fax that the lead time for component of product A has been increased to 3 weeks. a) Which other items are impacted? c) As the production planner, what ca the impact of the increase in the lead time for component C? One...
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty one units of Product Z are required in Period 10. (Assume that...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...