Question

- 16 Which of the following tailoring considerations is concerned with the teams background? Life cycle approach Physical lo
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 16. (C) Diversity

There are various tailoring considerations for project resource management that are Diversity, Physical Location, Industry-Specific resources, Acquisition of team members, team management, Diversity is the tailoring consideration that concern about the background of the team members, such as, language, nationality, culture, age, sex, color, knowledge, etc.

Answer 17. (A) Project Charter

Project Charter is the input to plan the resource management process. A project charter is a small and formal document that explain the project, its objectives, and people who are participating in the project.

Answer 18. (C) Force

There are five conflict management techniques in project management that are as follows,

  • Withdraw or Avoid.
  • Compromise or Reconcile
  • Smooth or Accommodate
  • Force or Direct
  • Collaborate or Problem Solving.

Given the case of Ayman and Hussain, is an example of Fore or Direct technique. where project managers use his powers to tell or direct the team members what to do. Project managers push their viewpoints and offer only win-lose situations. It is a dominating style of project manager where he wants to win his position and will ignore other member's concerns regarding the project.

Answer 19. (C) Manage Team

Manage Team is a resource management process that helps the project manager to track team member performance and productivity, give proper feedback, resolving conflicts and issues with team members and manage the changes in the team and project performance.

Note. As per the HOMEWORKLIB POLICY, I can answer only the first 4 questions or subparts. Thanks.

Add a comment
Know the answer?
Add Answer to:
- 16 Which of the following tailoring considerations is concerned with the team's background? Life cycle...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • I need help with my very last assignment of this term PLEASE!!, and here are the instructions: After reading Chapter T...

    I need help with my very last assignment of this term PLEASE!!, and here are the instructions: After reading Chapter Two, “Keys to Successful IT Governance,” from Roger Kroft and Guy Scalzi’s book entitled, IT Governance in Hospitals and Health Systems, please refer to the following assignment instructions below. This chapter consists of interviews with executives identifying mistakes that are made when governing healthcare information technology (IT). The chapter is broken down into subheadings listing areas of importance to understand...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT