Question

17) x ltd. began construction of a new building on ist jan, 2012. It obtained 21 lakh special loan to finance the Constructio

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Interest to be capitalized is = Interest on Specific borrowings and Interest on General borrowings The capitalisation rate reJournal entries :- Accounts Title & Explanation Credit $ Debit $ Date 31-Dec-12 Building (1020000+64793) 1,084,793 To Constru

Add a comment
Know the answer?
Add Answer to:
17) x ltd. began construction of a new building on ist jan, 2012. It obtained 21...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hart began construction of a new building last year on July 1, 2017. On the day...

    Hart began construction of a new building last year on July 1, 2017. On the day construction was started, the land was appraised at $350,000. It had been purchased 2 years earfier for $200,000. By Dec. 31, 2017 it had spent $600,000 on construction and correctly paid and capitalized interest in the amount of $32,000. The following added expenditures were made in 2018 prior to completion of the building on September 1, 2018: Date Amount Feb. 1, 2018 Aug.1, 2018...

  • Hart began construction of a new building last year on July 1, 2017. On the day...

    Hart began construction of a new building last year on July 1, 2017. On the day construction was started, the land was appraised at $350,000. It had been purchased 2 years earlier for $200,000. By Dec. 31, 2017 it had spent $600,000 on construction and correctly paid and capitalized interest in the amount of $32,000. The following added expenditures were made in 2018 prior to completion of the building on September 1, 2018: Date Amount Feb. 1, 2018 840,000 Aug.1,...

  • 127400 237600 1. Aequire Fixed Assets A. Interest During Construction Hart began construction of a new...

    127400 237600 1. Aequire Fixed Assets A. Interest During Construction Hart began construction of a new building last year on July 1, 2017. On the day construction was started the land was appraised at $350,000. It had been purchased 2 years earlier for $200,000 By Dec. 31, 2017 it had spent $600,000 on construction and correctly paid and capitalized interest in the amount of $32,000. 0 0 The following added expenditures were made in 2018 prior to completion of the...

  • Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October...

    Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...

  • 15 On January 1, 2020, Southtree Co. began construction of a building to be used as...

    15 On January 1, 2020, Southtree Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows: January $100,000 March 1 360,000 June 15 270,000 October 31" 153,000 On Jan. 1, 2020, the company obtained a $500,000 specific construction loan with a 6% interest rate. The loan was outstanding during the entire construction period. The company's other interest-bearing...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: points $5.829.oe. 17% bonds $3.880.880.13% long-term note Construction expenditures incurred during 2021 were as follows: $ January 1 March 31 June 30 September 30 December 31 820,000 1,420.000...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 January 30, 2022 $ 400,000 600,000 600,000 540,000 The company's fiscal year-end is December 31. Required: Calculate...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT