Question

What two numbers are needed to determine the total cost of your project based on both...

What two numbers are needed to determine the total cost of your project based on both the current project performance and the remaining work? (select the two best answers)

A.

EAC

B.

AC

C.

BAC

D.

ETC

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Estimate at Completion (EAC): The total cost of your project based on both the current project performance and the remaining work. The formula for the ECA is ECA= AC+ ETC. The EAC is the addition of two numbers, that is, AC and ETC.

As per the question, need to select two numbers. Hence option A is incorrect.

Budget at Completion: The total amount of budget required to complete the project which is estimated at the start of the project.

Hence option C is incorrect.

Actual Cost: The actual amount of money required to complete an activity or to acquire a product. It is one of the required numbers to determine the total cost of your project based on both the current project performance and the remaining work.

Hence option B is correct.

Estimate to complete: It is defined as the total cost of the project required to complete the remaining work from a given date. It is one of the required numbers to determine the total cost of your project based on both the current project performance and the remaining work.

Hence option C is correct.

Therefore, the two numbers are needed to determine the total cost of your project based on both the current project performance and the remaining work are AC and ETC.

Add a comment
Know the answer?
Add Answer to:
What two numbers are needed to determine the total cost of your project based on both...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • 4. You are the project finance manager on a project that is coming in over budget...

    4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

  • Your project exceeded costs in the past caused by an underestimation of resource costs in the...

    Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at 51.000.000, what should be your new EAC (estimate at completion)? A) $1.800.000 B) $2.000.000 C) $2.200.000 D) $2.400.000

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT