Question

2. King Supply makes four different types of plumbing fixtures: W, X, Y and Z. The contribution margins for these products are: $70 for Product W, 560 for Product X, $90 for Product Y and S100 for Product Z. Fixed overhead is estimated at S5,500 per week. The manufacture of each fixture requires four machines, Machines #1, 2, 3 and 4, Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other. The processing requirements to make one unit of each product are shown in the table. Weekly product demand for the next planning period has been forecasted as follows: 70 WS, 60 50 Ys and 30孫 In all the questions below show calculations as needed Note: 1. Fixtures W, X,Y and Z are the Products of King Supply company (equivalent to products Contribution Margins of the products are already given C. D in the homework problem 2. Processing Time (Minutes Per Fixture Fixture MachineMachine 2 Machine 3 Machine 4 20 15 A) Use the information in above table, which machine is the bottleneck operation? (5 Points) A) Machine 1 B) Machine 2 C) Machine 3 D) Machine 4 Answer: B) Use the information in the above table and using the bottleneck method, in what sequence should products be scheduled for production? (5 Points) A)Z, Y, X, W B) X, W, Z, Y C) Z, Y, W, X D) X, Y, Z, W Answer:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A) Answer: A) Machine 1

Workload of machine 1 = 10*70+5*60+20*50+15*30 = 2450 minutes

Workload of machine 2 = 15*70+10*60+5*50+5*30 = 2050 minutes

Workload of machine 3 = 10*70+15*60+5*50+5*30 = 2000 minutes

Workload of machine 4 = 5*70+10*60+10*50+10*30 = 1750 minutes

Available capacity per machine = 40 hours* 60 minutes per hour = 2400 minutes

Workload of machine 1 is more than its capacity. Therefore, Machine 1 is the bottleneck.

B) Answer: B) X,W, Z, Y

Using bottleneck method, we need to determine the profit contribution per minute of bottleneck resource (Machine 1)

Profit contribution per minute of bottleneck resource for product W = 70/10 = $ 7

Profit contribution per minute of bottleneck resource for product X = 60/5 = $ 12

Profit contribution per minute of bottleneck resource for product Y = 90/20 = $ 4.5

Profit contribution per minute of bottleneck resource for product Z = 100/15 = $ 6.7

The products are scheduled in order of their profit contribution per minute of bottleneck resource. So the optimal schedule is: X,W, Z, Y

C) Answer: C) 70 W, 60 X, 47 Y, 30 Z

Product X, W and Z can be produced upto their respective demand level. Remaining time on Machine 1 = 2400 - (5*60+10*70+15*30) = 950 minutes

Quantity of Product Y that can be produced in remaining time = 950/20 = 47.5 ~ 47

D) Answer: B) greater than $ 10000 but less than or equal to 11000

Profit = Profit contribution from products - Fixed overhead cost

= (70*70+60*60+47*90+30*100)-5500

= $ 10,230

Add a comment
Know the answer?
Add Answer to:
2. King Supply makes four different types of plumbing fixtures: W, X, Y and Z. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2 Schmidt Industries makes four different snake traps; the Harlan, the Gaylen, the Leah and...

    Problem 2 Schmidt Industries makes four different snake traps; the Harlan, the Gaylen, the Leah and the Matthew. The Harlan sells for $200 and has $80 in parts; the Gaylen sells for $150 and requires $60 in parts; the Leah sells for $100 and has $40 in parts; and the Matthew sells for $75 but requires $20 of parts. Schmidt Industries has four machines (we'll call them A, B, C, and D for convenience) that are used in the production...

  • A company makes four products: Product A sells for $50 but needs $10 of materials; Product...

    A company makes four products: Product A sells for $50 but needs $10 of materials; Product B sells for $75 but needs $30 of materials; Product C sells for $100 but needs $50 of materials; Product D sells for $150 but needs $75 of materials. The labor cost is $15/hr. The processing requirements for each product on each of the four machines are shown in the table. Table 6 Work Center Processing Time (min/unit) A B C D W 3...

  • A company makes two products (X and Y) using two machines (A and B). Each unit...

    A company makes two products (X and Y) using two machines (A and B). Each unit of X that is produced requires 50 minutes processing time on machine A and 30 minutes processing time on machine B. Each unit of Y that is produced requires 24 minutes processing time on machine A and 33 minutes processing time on machine B. At the start of the current week there are 30 units of X and 90 units of Y in stock....

  • A company would like to determine the best production schedule using a manufacturing process with four...

    A company would like to determine the best production schedule using a manufacturing process with four machines: W, X, Y, and Z. Each machine can be used for 2400 minutes per week. The weekly demands and the processing time on machines are shown below. Product A, 150 units/week, 6, 10, 6, 0 minutes; Product B, 90 units/week, 0, 9, 7, 8 minutes; Product C, 120 units/week, 8, 8, 7, 5 minutes; Product D, 130 units/week, 7, 0, 5, 8 minutes....

  • ABC Company produces Product X, Product Y, and Product Z. All three products require processing on...

    ABC Company produces Product X, Product Y, and Product Z. All three products require processing on specialized finishing machines. The capacity of these machines is 2,250 hours per month. ABC Company wants to determine the product mix that should be achieved to meet the high demand for each product and provide the maximum profit. Following is information about each product: Product X Product Y Product Z Selling price $ 151 $ 120 $ 38 Variable costs 105 58 30 Machine...

  • A company manufactures four products (1,2,3,4) on two machines (X and Y). The time (in minutes)...

    A company manufactures four products (1,2,3,4) on two machines (X and Y). The time (in minutes) to process one unit of each product on each machine is shown below:, Product 1 in X = 10 min , in Y= 27 min Product 2 in X = 12 min , in Y =19 min Product 3 in X =13 min,in Y =33 min Product 4 in X = 8 min,in Y =23 min The profit per unit for each product (1,2,3,4)...

  • Springer Products manufactures three different product lines, Model X, Model Y, and Model Z. Considerable market...

    Springer Products manufactures three different product lines, Model X, Model Y, and Model Z. Considerable market demand exists for all models. The following per unit data apply: Model X $50 Model Y $63 Model Z $72 Selling price Direct materials Direct labor ($13 per hour) Variable support costs ($4 per machine - hour) Fixed support costs ūcco ü co co co Which model has the greatest contribution margin per machine - hour? O A. Model X O B. Model Y...

  • solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is...

    solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S,...

  • Springer Products manufactures three different product lines, Model X, Model Y, and Model Z. Considerable market...

    Springer Products manufactures three different product lines, Model X, Model Y, and Model Z. Considerable market demand exists for all models. The following per unit data apply: Model X Model Y Model Z $71 $69 Selling price Direct materials Direct labor ($13 per hour) Variable support costs ($5 per machine - hour) Fixed support costs Which model has the greatest contribution margin per unit? O A. Model X OB. Model Y O C. Model z OD. Both Model X and...

  • j Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B,...

    j Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT