Question

The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequenceSuppose demand is 50 toothbrushes per hour. What is the е. takt time (seconds)? Suppose the takt time is 50 seconds. What is

0 0
Add a comment Improve this question Transcribed image text
Answer #1

worker

time

1

95

2

23

3

43

4

37

5

82

Answer a: Labor content = sum of task time =95+23+43+37+82 = 280 secs

Worker 1 is the bottleneck of the process, because worker 1 takes 95 secs to perform his tasks. Its process capacity is 60/95= 0.63 units per min or 37.89 units per hour

Direct labour cost per unit = total wages per hour/ units per hour

wages per hour= $ 24

Answer b: Direct labour cost per unit = $24*5/37.89 =$3.17 per toothbrush

Answer c: cycle time= 95 secs, idle time for worker A= 0 secs

labor utilization worker A= effective cycle time/cycle time of the system= 95/95= 1.0

Answer d: idle time= bottleneck time- process time

worker

process time

idle time= 95-process time

1

95

0

2

23

72

3

43

52

4

37

58

5

82

13

Total

280

195

  • Average labor utilization = total labour content / (labour content + total idle time)

Average labour utilization= 280/(280+195)= 0.59

Add a comment
Know the answer?
Add Answer to:
The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there...

    The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequence of assembly steps performed by five workers. Each worker does two tasks. Workers are paid $15 per hour. Worker Task Time (seconds) A T1 40 A T2 25 B T3 20 B T4 15 C T5 10 C T6 15 D T7 10 D T8 20 E T9 25 E T10 35 Instruction: Round "cost of direct labor" and "average labor...

  • Imagine US is a startup that offers high-definition 3-D prenatal ultrasounds for high-end customers. The service...

    Imagine US is a startup that offers high-definition 3-D prenatal ultrasounds for high-end customers. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses):Activity 1: Welcome a patient and explain the procedure. (7 minutes)Activity 2: Prep the patient (e.g., show them to the room, apply ultrasound gel). (3 minutes)Activity 3: Take images. (14 minutes)Activity 4: Analyze images. (9 minutes)Activity 5: Discuss diagnostic with patient. (23 minutes)They...

  • Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services...

    Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): Activity 1: Welcome a guest and offer homemade herb tea (12 minutes). Activity 2: Wash and condition hair (12 minutes). Activity 3: Neck, shoulder, and back stress-release massage (12 minutes)....

  • Part 1.C&A Fast Food has four activities in serving a customer: greet customer, take order, process...

    Part 1.C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows: ActivityProcessing time per customer Greet customer 2 seconds Take order 30 seconds Process order 60 seconds Deliver order 5 seconds. a. What is the average labor utilization? b.Assume demand is unlimited. If one additional employee is added...

  • Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--...

    Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--‐paced line flow). Each worker must perform at least one task. Time to Complete Task (seconds): Task 1: 26 Task 2: 25 Task 3: 15 Task 4: 24 Task 5: 15 Task 6: 20 Task 7: 47 Task 8: 15 Task 9: 20 Task 10:25 Task 11: 15 Task 12: 20 The current conveyor--paced assembly-‐line configuration assigns the workers in the following...

  • PA 4-4 (Algo) Mr. K's is a very popular hair salon. It... Mr. K's is a...

    PA 4-4 (Algo) Mr. K's is a very popular hair salon. It... Mr. K's is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): Activity 1: Welcome a guest and offer homemade herb tea (9 minutes). Activity 2: Wash and condition hair...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

  • Operations Management

    In the molding shop, there are 11 machines capable of molding the one part done in-house, but historically one machine is always being maintained or repaired at any given time. Each machine requires a full-time operator who earns an hourly wage of $15, though only 50 minutes of a molding operator's typical hour is occupied with the tasks of loading, unloading, actively monitoring, and adjusting the machine. The machines can each produce 25 parts per hour. The workers will work...

  • Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services...

    Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): Activity 1: Welcome a guest and offer homemade herb tea (11 minutes). Activity 2: Wash and condition hair (11 minutes). Activity 3: Neck, shoulder, and back stress-release massage (11 minutes)....

  • Part I – Process and Capacity Analysis Mortgage, Inc. processes loan applications in a “back-office” service...

    Part I – Process and Capacity Analysis Mortgage, Inc. processes loan applications in a “back-office” service facility. Each loan application must undergo a sequence of three separate processing activities before Mortgage, Inc. can make a decision to approve or decline the application. That is, a loan application first passes through Activity 1, then Activity 2, and finally Activity 3. Each activity has a fixed number of workers (given below). For example, there are three workers assigned to Activity 1 and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT