Question

Part I – Process and Capacity Analysis Mortgage, Inc. processes loan applications in a “back-office” service...

Part I – Process and Capacity Analysis

Mortgage, Inc. processes loan applications in a “back-office” service facility. Each loan application must undergo a sequence of three separate processing activities before

Mortgage, Inc. can make a decision to approve or decline the application. That is, a loan application first passes through Activity 1, then Activity 2, and finally Activity 3. Each activity has a fixed number of workers (given below). For example, there are three workers assigned to Activity 1 and these three workers only perform Activity 1. An application only needs to be processed by one worker at an activity; therefore, different applications can be processed simultaneously by different workers assigned to the same activity. Each activity has an associated processing time (given below). For example, it takes one worker 18 minutes to perform Activity 1 for an application. Ignore startup and shutdown effects in answering the questions below. Applications arrive at a rate of 7 per hour. (This is the demand rate.)

Note the following definitions from class (or in addition to those provided in class).

Process capacity = bottleneck capacity

Process flow rate (or “Flow rate”) = minimum of demand rate and process capacity

Utilization of stage n = Flow rate / Capacity of stage n

Activity Processing time (min/unit) Number of workers
1 18 3
2 15 2
3 22 4

1) What is the capacity of each activity, measured in applications per hour?

2) Which activity is the bottleneck?

3) What is the capacity of the facility in applications per hour?

4) What is the flow rate of the facility, and what are the utilizations of each Activity?

5) If they hired an additional worker for Activity 1, what would be the capacity of the

facility? What explains this result?

6) What would the utilizations of each Activity be in this case? Provide a brief

explanation of your result.

7) If they hired an additional worker for Activity 2, but kept Activity 1 at 3 workers,

what would be the capacity of the facility? What explains this result?

8) Use the number of workers in Question 7. If the demand rate increased to 11

applications per hour, what would be the flow rate of the facility, and the utilizations

of each Activity?

Part II – Claims Processing

An insurance agency wants to analyze its claims process. There are two steps in the process: evaluation and payment processing. When a customer claim arrives at the agency, it is first evaluated to see if it is a legitimate claim, where the customer would receive a payment. If it is indeed legitimate, the claim goes to payment processing, where additional checks are performed and the agency cuts a check to the customer. The agency on average receives 30 claims per day. There are on average 15 cases under evaluation and 24 cases in payment processing every day. Only 40% of the cases will pass evaluation and enter payment processing; the other cases are denied payment and terminated. What is the average total processing time per case in this agency?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. No of apps each worker can process in an hour : 60/processing time

Capacity of each activity : No of worker x no of apps processed in hr by each worker

Using above arithmetic, we get capaciy of each unit as :

Activity Processing time (min/unit) Number of workers Hourly Capacity of Activity (no of apps)
1 18 3 10
2 15 2 8
3 22 4 10

2. Actitivy 2 is the bottleneck as it has minimum capacity

3. Capacity of the process is the capacity of the bottleneck i.e. 8 unit per hour

4. Flow rate is the minimum of demand and process capacity. Whilst capacity of the process is 8 apps per hour but demand is only 7 apps per hours. Hence flow rate is 7 apps per hr.

5. There will be no impact to process capacity (stays at 7 apps per hr) if a person is hired for Activity 1 as it is not a bottleneck.

6. With additional hire for activity 1, utilization and capacity will be as :

Activity Processing time (min/unit) Number of workers Hourly Capacity of Activity (no of apps)
1 18 4 13
2 15 2 8
3 22 4 10

7. If additional worker is hired for activity 2 then capacity will change as per below

Activity Processing time (min/unit) Number of workers Hourly Capacity of Activity (no of apps)
1 18 3 10
2 15 3 12
3 22 4 10

This will improve the process capacity from 8 to 10.

8. If the demand rate increased to 11, then we will compare the process rate and demand and the lower of the two will be the flow rate. In this case, flow rate will be 10.

Part II

No of cases post evaluation is 40% of assessment capacity = 0.4*15 = 6 cases per day.

Even against a higher payment processing capacity of 24 cases, only 6 cases can be processed per day.

Lower of process capacity of 6 Vs demand of 30 applications per day, gives us a flow rate of 6 applications per day. In a day of 8 hrs, processing time per case will be (8*60)mins/6 i.e. 80 minutes per application.

Add a comment
Know the answer?
Add Answer to:
Part I – Process and Capacity Analysis Mortgage, Inc. processes loan applications in a “back-office” service...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 3 D'Mortgage's primary business is processing mortgage loan applications. In 20X1, the manager of D'Mortgage's...

    Question 3 D'Mortgage's primary business is processing mortgage loan applications. In 20X1, the manager of D'Mortgage's loan department established a policy of charging $300 fee for every loan application processed. 20X2's costs have been projected as follows: Variable costs: Loan consultant's salaries: $18 per hour (a loan application takes 5 hours to process) Supplies: $3.60 per application Other variable costs: $6.40 per application Annual fixed costs Depreciation of equipment: $9,200 Building rental: $15,500 Promotional costs: $13,500 Other fixed costs: $9,800....

  • The local driver’s license center processes applications for driver’s license renewals through the following three steps....

    The local driver’s license center processes applications for driver’s license renewals through the following three steps. First, the customer registers with the receptionist, who updates the customer’s information in the database. This first step takes 3 minutes per customer. Then, the customer visits one of 1 cashiers to pay the associated fees for the license renewal. This takes 3 minutes per customer because several forms must be printed from the computer and signed by the customer. Finally, the customer visits...

  • ABC Costing for a Service Organization Fairfield Mortgage Company is a full-service residential mortgage company in...

    ABC Costing for a Service Organization Fairfield Mortgage Company is a full-service residential mortgage company in the Atlanta area that operates in a very competitive market. The CEO, Richard Sissom, is concerned about operating costs associated with processing mortgage applications and has decided to install an ABC costing system to help him get a handle on costs. Although labor hours seem to be the primary driver of the cost of processing a new mortgage, the labor cost for the different...

  • Consider a process consisting of three activities required to make a cell phone case. Assume there exists

    Consider a process consisting of three activities required to make a cell phone case. Assume there exists an unlimited demand for the cases. • Activity 1 has a processing time of 6 minutes per unit. • Activity 2 has a processing time of 3 minutes per unit. Activity 3 has a processing time of 5 minutes per unit. All three activities are staffed by one worker and each worker gets paid $12 per hour. A. Calculate the cost of direct...

  • Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North...

    Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North California facility, they make tables. All parts of the table are purchased except for the tabletop that is fabricated at the plant. Tables are made to order for dealers who FAX orders into the sales department. Orders are processed from the order database on FIFO basis. The first step in the process is to cut the top ¾ pressboard. It takes one worker 20...

  • PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption...

    PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....

  • I need help on part a, b, c of this question. Please help me by show...

    I need help on part a, b, c of this question. Please help me by show working and explanation at how you arrived at the answer. Thank you! 2. Northern Coffee follows the flow chart below to serve its customers. Note that some triangles may be omitted intentionally. It takes a worker one minute to take order and receive payment, two minutes to prepare coffee, and three minutes to clean the equipment. Take order and receive payment Clean equipment Prepare...

  • Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one ta...

    Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. Assume that the process is capacity constrained (so the demand rate...

  • HEAVYLOAD INC has 3 resources (Resource A, Resource B and Resource C) in its production process....

    HEAVYLOAD INC has 3 resources (Resource A, Resource B and Resource C) in its production process. The production process involves 3 products (Product A, Product B and Product C) being processed through these 3 resources. Currently, there is demand for 700 units of Product A, 1,200 units of Product B and 200 units of Product C per hour. The following bullets provide information about each resource: At Resource A, the processing time for Product A is 14.112 seconds and for...

  • Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the...

    Atlas Inc. is a toy bicycle manufacturing company producing a five inch small version of the bike that Lance Armstrong rode to win his first Tour de France. The assembly line at Atlas Inc. consists of seven work stations, each performing a single step. Stations and processing times are summarized here: Step 1 (50 sec.): The plastic tube for the frame is cut to size. Step 2 (40 sec.): The tube is put together. Step 3 (55 sec.): The frame...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT