Question


You have developed the following simple product structure of tems needed for your gift bag for a rush party for are expected to have the gift bags ready at 5 P.M. However, you need to personalize the items assemble 200 Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K (2 hours), tem L and iterm M (4 hours) Develop a Sime-phased assembly plan to prepare the gift bags prospective pledges in your organization. You forecast 200 attendees. You (monogrammed pens, ncte pads, iterature from the printer, etc.). The lead time is 1 hour to Cick the ion to view the product structure Choose the comrect time-phased assembly plan to prepare the gift bgs
O A. ов. 11 12 10 11 12 AM PM PM O c. O D. 10 11-12.T-ㄒㄒㄒㄧ厂. 1112 AM AM PM PM
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution : Option : B

A : Incorrect : Lead time for K is 2 hours.

B : Correct

C : K is not a subpart of L

D : L is not a subpart of K

Add a comment
Know the answer?
Add Answer to:
You have developed the following simple product structure of tems needed for your gift bag for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT