Question

Given the following data: Flexible budget variance 100 F Efficiency variance 50% of spending variance, and...

Given the following data:
Flexible budget variance 100 F
Efficiency variance 50% of spending variance, and unfavorable
Standard rate 10
Machie hours 200
Find
Standard hours

$220

$210,000

150,000

100,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Statement showing Computations
Spending variance = 100*50% = 50 U
DLEV = (SH-AH)SR
-50 = (SH -200)10
-5 =(SH -200)
Standard hours = 200 - 5 =195 hours
Add a comment
Know the answer?
Add Answer to:
Given the following data: Flexible budget variance 100 F Efficiency variance 50% of spending variance, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given for Umbrella Corporation's variable manufacturing overhead costs: $2,500 favorable flexible-budget variance; $2,500 unfavorable efficiency variance....

    Given for Umbrella Corporation's variable manufacturing overhead costs: $2,500 favorable flexible-budget variance; $2,500 unfavorable efficiency variance. The spending variance is closest to: a. $0 b. $5,000 F c. $5,000 U d. Indeterminate

  • ABC Company has the following standards and flexible budget data: Standard Variable Overhead Rate $5.40 Per...

    ABC Company has the following standards and flexible budget data: Standard Variable Overhead Rate $5.40 Per direct labour hour Standard quantity of direct labor $1.80 hours per unit of output Budgeted fixed overhead rate $100,000 Budgeted Output 25,000 units Standard Variable Overhead $10.80 per unit Standard Fixed Overhead $3.60 per unit Actual Results for November are given below: Actual Output 30,000 units Actual variable overhead $360,000 Actual Fixed Overhead $106,000 Actual Direct Labor 56,000 hours REQUIRED: A) Variable manufacturing overhead...

  • Required: What is the flexible-budget variance for variable manufacturing overhead! Skizone Company's 4-Variance Analysis: Spending Variance...

    Required: What is the flexible-budget variance for variable manufacturing overhead! Skizone Company's 4-Variance Analysis: Spending Variance Efficiency Variance Production- Volume Variance Variable overhead S6400 F Fixed overhead (a) 2 $13.000 U No variance $46.000 US Required: If Skizone's combined 4-Variance Analysis shows an unfavorable spending varian S2000, what is the fixed overhead spending variance (a)? Chapters porta Achel ARXAS 81760 AQXSK 065 x LAZ 12500 3R - SE

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units 2...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units 2 Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $424,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,800 machine hours and incurred $689,000 in total manufacturing overhead cost to manufacture 42,070 units. Actual fixed overhead cost for the year was $437,000. Required: Determine for the...

  • Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000...

    Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 376,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,200 machine hours and incurred $637,000 in total manufacturing overhead cost to manufacture 42,010 units. Actual fixed overhead cost for the year was $386,000. Required: Determine for...

  • Crystal Glassware Company has the following standards and flexible-budget data. Standard variable-overhead rate Standard quantity of...

    Crystal Glassware Company has the following standards and flexible-budget data. Standard variable-overhead rate Standard quantity of direct labor Budgeted fixed overhead Budgeted output $ 6.00 per direct-labor hour 2 hours per unit of output $144,000 24,000 units Actual results for April are as follows: 1 + Actual output Actual variable overhead Actual fixed overhead Actual direct labor 17,000 units $306,000 $141,000 50,000 hours Required: Use the variance formulas to compute the following variances. (Indicate the effect of each variance by...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity i...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 26 setups and 26,000 machine hours to manufacture 6,500 units for the year. Selected data for 2019 follow Budgeted fixed factory overhead: $ 54,600 178,000 Setup cost Other $232,600 $481,000 Total factory overhead cost incurred Variable factory overhead rate: $ 400 $6.00 30,000 34,500 Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead 40,000 units 2 $3.00 per machine hour $352,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 87,000 machine hours and incurred $619,000 in total manufacturing overhead cost to manufacture 42,190 units. Actual fixed overhead cost for the year was $371,000. Required: Determine for the...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $368,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 88,000 machine hours and incurred $636,000 in total manufacturing overhead cost to manufacture 43,000 units. Actual fixed overhead cost for the year was $380,000. Required: Determine for the year:...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32 setups and 32,000 machine hours to manufacture 6,400 units for the year. Selected data for 2019 follow: $ 102,400 174,000 $276,400 $496,000 Budgeted fixed factory overhead: Setup cost Other Total factory overhead cost incurred Variable factory overhead rate: Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number of setups Actual number of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT