Question

Project ALPHA has 6 Activities from A to F as follows: Activity Duration Preceded By A 5 B А С 7 A D 6 B 7 c E F E The number

Also find the total float activity of E ...
Number of the critical path is ...
The late finish of activity F is...

thank you,
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : Part C 0

The critical activity is an activity at the merging end of a merging event in the network diagram. This network does not have a merging event.

It has 2 paths :

A-B-D

A-C-E-F

Also find the total float activity of E = 12-12 = 0

Number of the critical path is 2

The late finish of activity F is 20

Add a comment
Know the answer?
Add Answer to:
Also find the total float activity of E ... Number of the critical path is ......
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT