Sand Castle Manufacturing produces concrete yard art. Recently, 2,500 concrete seahorses were produced in a production run. The run required 1,250 machine hours, and also required five "set-ups" of mixing equipment. Final inspection required 50 hours of inspection activity. Overhead is estimated at $30 per machine hour, plus $2,750 per "set-up," and $25 per inspection hour. Direct materials and direct labor total $75 per seahorse. (a) Apply activity-based costing and determine the amount assigned to a concrete seahorse. (b) For GAAP purposes, Sand Castle applies traditional costing methods, and allocates overhead at $50 per machine hour. How much cost would be assigned to the 2,500 seahorses? What is the per unit cost of a seahorse under the traditional approach? What might explain the higher cost assignment, and how could this influence business decision making?
Solution a:
Computation of cost assingned to Concrete Seahorse - Activity based costing | |
Particulars | Amount |
Direct material & Direct labor (2500*$75) | $187,500.00 |
Overhead cost - Machining (1250*$30) | $37,500.00 |
Overhead cost - Setup (5*$2750) | $13,750.00 |
Overhead cost - Inspection (50*$25) | $1,250.00 |
Total amount assigned to concrete seahorse | $240,000.00 |
Solution b:
Computation of cost assingned to Concrete Seahorse - Traditional costing | |
Particulars | Amount |
Direct material & Direct labor (2500*$75) | $187,500.00 |
Overhead cost (1250*$50) | $62,500.00 |
Total amount assigned to concrete seahorse | $250,000.00 |
Per unit cost of seahorse under traditional approach = $250,000 / 2500 = $100 per seahorse
As traditional approach is resulting in higher cost assignment,
the reason for the same is that in traditional approch overhead is
allocated using plantwide single overhead rate while in activity
based costing overhead was assigned to activities indentified and
applied to product on the basis of actual usage of activity. Thus
activity based costing show the accruate cost of product rather
than traditional approach. In this case traditional cost resulting
in higher cost assignment that influence business decision like
product pricing, accepting or rejecting the order. As cost is
higher it will result in setup higher product price that may result
in not able to sale desired quantity.
Sand Castle Manufacturing produces concrete yard art. Recently, 2,500 concrete seahorses were produced in a production...
Sand Castle Manufacturing produces concrete yard art. 2,600 concrete seahorses were produced in a recent production run. The run required 1,300 machine hours, and also required 6 "set-ups" of mixing equipment. Final inspection required 60 hours of inspection activity. Estimated overhead is estimated at $40 per machine hour, plus $2,800 per "set-up" and $30 per inspection hour. Direct materials and direct labor total $80 per seahorse. (a) Apply activity-based costing and determine the amount assigned to a concrete seahorse. A....
Backyard Playground produces childrens swing-sets. 4,500 swing-sets were produced in a recent production run. The run required 1,500 machine hours, and also required four "set-ups" of equipment. Final inspection required 75 hours of inspection activity. Estimated overhead is estimated at $25 per machine hour, plus $3,500 per "set-up" and $20 per inspection hour. Direct materials and direct labor total $500 per swing-set. a) Apply activity-based costing and determine the amount assigned to a swing-set. b) For GAAP purposes, Backyard Playground...
Problem 5.37A a-b Jacobson Electronics manufactures two HD television models: the Royale, which sells for $1,400, and a new model, the Majestic, which sells for $1,100. The production costs calculated per unit under traditional costing for each model in 2020 were as follows: Royale Majestic 1600 Traditional costing Direct materials Direct labour ($20 per hour) Manufacturing overhead ($35 per direct labour hour) Total per unit cost 100 140 175 $875 $540 In 2020, Jacobson manufactured 20,000 units of the Royale...
The Homer Corporation produces two products, and reports the following production and cost information for the most recent accounting period Product A Product B Number of units produced 15,e80 units 2,500 units Direct labor $25 per direct labor hour (DLH) Direct materials cost 0.50 DLH per unit $ 2 per unit 2.00 DLH per unit $ 30 per unit Activity Driver Overhead costs Machine setup Quality inspections Total Total Cost $ 3,000. etups Product A 5 setups Product B 20...
Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...
8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...
7. Ryan Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Assembly..... $698,950 35,000 machine-hours Processing orders ....... $85,101 1,900 orders Inspection ......... $107,440 1,580 inspection-hours Data concerning the company's product P58Z appear below: Annual unit production and sales...... 400 Annual machine-hours...... 1,000 Annual number of orders. 90 Annual inspection hours.......... 30 Direct materials cost ........ $34.78 per unit Direct labor cost... $23.52 per unit According to the activity-based costing system,...
Carter, Inc. produces two different products, Product A and Product B. Carter uses a traditional volume-based costing system in which direct labor hours are the allocation base. Carter is considering switching to an ABC system by splitting its manufacturing overhead cost of $783,000 across three activities: Design, Production, and Inspection. Under the traditional volume-based costing system, the predetermined overhead rate is $2.61/direct labor hour. Under the ABC system, the rate for each activity and usage of the activity drivers are...
ACCT 210 Chapter 5 Supplemental in Class Assignment Numbers Text Model A Product Data Model B 100,000 110,000 10,000 Units produced per year Direct Labor hours Production Set-ups Inspection hours Machine hours Maintenance hours 50,000 40 800 20,000 10,000 350,000 60 1,200 180,000 90,000 400,000 100 2,000 200,000 100,000 Total Activity Rate Overhead costs: Set-up Costs Inspection costs Machining Costs Maintenance Costs 300,000 250,000 240,000 210,000 1,000,000 Activity Driver Pr00015 Inspection hours Machine hog Maintenance hours nu 1. Compute the...
Coronado Company produces two products: MB-R and MB-X. Currently, Coronado allocates overhead based on direct labour hours. Overhead is estimated at $436,800. The cost accountant realizes that there are some differences in how resources are being used in producing these two components and is considering the use of ABC to allocate overhead. She determines that overhead is caused by testing and inspections, $112,000; machine setup, $84,000; machine stamping, $200,000; and plant maintenance, $40,800. Coronado estimates the following activities related to...