Question

In this problem, you are to test the validity of your forecasting model. Here are the forecasts for a model you have been usi

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

Week Forecast Actual Deviation RSFE Absolute deviation Sum of absolute deviation MAD TS
1 840 920 80 80 80 80 80 1.0
2 870 1,020 150 230 150 230 115 2.0
3 970 1,070 100 330 100 330 110 3.0
4 970 920 -50 280 50 380 95 2.9
5 1,020 920 -100 180 100 480 96 1.9
6 995 1,010 15 195 15 495 82.5 2.4

Calculations:

ДА В с С D E Week Forecast Actual Deviation MAD TS Noo 840 870 970 970 1020 920 1020 1070 920 920 1010 =D3-C3 =D4-C4 =D5-C5 =

(b)

Unacceptable since the TS values are outside the limit [-2, 2].

Add a comment
Know the answer?
Add Answer to:
In this problem, you are to test the validity of your forecasting model. Here are the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 3-23 After using your forecasting model for six months, you decide to test it using...

    Problem 3-23 After using your forecasting model for six months, you decide to test it using MAD and a tracking signal. Here are the forecast and actual demands for the six-month period: PERIOD May June July August September October FORECAST 425 475 520 600 630 690 ACTUAL 495 510 395 505 700 560 a. Find the tracking signal. (Negative values should be indicated by a minus sign. Round your answers to 2 decimal places.) Tracking Signal Period May June July...

  • After using your forecasting model for six months, you decide to test it using MAD and...

    After using your forecasting model for six months, you decide to test it using MAD and a tracking signal. Here are the forecast and actual demands for the six-month period: PERIOD FORECAST ACTUAL May 410 470 June 460 525 July 510 370 August 615 505 September 635 685 October 710 575 a. Find the tracking signal. (Negative values should be indicated by a minus sign. Round your answers to 2 decimal places.) Period Tracking Signal May June July August September...

  • A particular forecasting model was used to forecast a six-month period. Here are the forecasts and...

    A particular forecasting model was used to forecast a six-month period. Here are the forecasts and actual demands that resulted: FORECAST ACTUAL April 258 358 May 332 482 June 407 507 July 357 307 August 382 282 September 457 582 a. Find the tracking signal for each month. (Negative values should be indicated by a minus sign. Round your answers to the 2 decimal places.) b. Is the model being used is giving acceptable answers. No, the model's performance is...

  • The following table shows predicted product demand using your particular forecasting method along with the actual...

    The following table shows predicted product demand using your particular forecasting method along with the actual demand that occurred: FORECAST ACTUAL 1,490 1,540 1,390 1,490 1,690 1,590 1,742 1,640 1,790 1,690 a. Compute the tracking signal using the mean absolute deviation and running sum of forecast errors. (Negative values should be indicated by a minus sign. Round your "Mean Absolute Deviation", "Tracking Signal" to 2 decimal places and all other answers to the nearest whole number.) Period Forecast Actual Deviation...

  • Exercise # 1-0M6322-week 4-Forecasting using Exponential Smoothing The first five periods of demand data are shown...

    Exercise # 1-0M6322-week 4-Forecasting using Exponential Smoothing The first five periods of demand data are shown in the following table Let the smoothing coefficient, alpha, equal 0.2.Compute the exponentially smoothed forecasts for periods one through four Initialize the procedure with a forecast value for period one of 37 Period Aggregate Demand Forecast demand 38 42 40 36 42 37 Determine the Running Sum of Forecast Errors (RSFE), the Mean Absolute Deviation, MADt Land the Tracking Signal(TS) at the end of...

  • You want to compare how two forecasting methods would perform on some historical sales data. You...

    You want to compare how two forecasting methods would perform on some historical sales data. You will forecast the sales for months 4 through 19, calculate the mean absolute deviation (MAD) for both methods, and you can claim that the one that has lower MAD performed better, at least for the historical data. a) The first method is known as the moving average method. The forecast for a month will be the average sales of three previous months. So, forecast...

  • Problem 2: Forecasting (10 points) Given these sales figures over the last 6 weeks, your boss needs you to test two...

    Problem 2: Forecasting (10 points) Given these sales figures over the last 6 weeks, your boss needs you to test two different forecasting methods (parts a and b below) to determine which method is best. For your measure of "best", recommend to your boss that the company should use the method with the lowest mean absolute deviation (MAD). Then use that method to provide your forecast for week 7 in part c. Week UWN Unit Sold 523 587 622 601...

  • Problem 2: Forecasting (10 points) Given these sales figures over the last 6 weeks, your boss...

    Problem 2: Forecasting (10 points) Given these sales figures over the last 6 weeks, your boss needs you to test two different forecasting methods (parts a and b below) to determine which method is best. For your measure of "best", recommend to your boss that the company should use the method with the lowest mean absolute deviation (MAD). Then use that method to provide your forecast for week 7 in part c. Week >WN Unit Sold 523 587 622 601...

  • If you could please provide!! Thank you!! ▪ Necessary and appropriate assumptions (when applicable) ▪ Formulas...

    If you could please provide!! Thank you!! ▪ Necessary and appropriate assumptions (when applicable) ▪ Formulas and graphs ▪ Relevant conclusion(s) 4. .The following table shows predicted product demand using your particular forecasting method along with the actual demand that occurred: FORECAST AcTUAL 1,500 1,550 400500 1,700 1.750 1,800 1,600 1,650 1,700 a. Compute the tracking signal using the mean absolute deviation and running sum of forecast errors. Discuss whether your forecasting method is giving good predictions. b.

  • A manager has been using a certain technique to forecast demand for project management software at...

    A manager has been using a certain technique to forecast demand for project management software at her store. Actual demand and her corresponding predictions are shown below: MonthActual Demand Manager's Forecast March4545April4250May3445June4840July3845 a. What was the manager's forecast error for each month?b. What is the mean error (ME), the mean squared error (MSE), the mean absolute deviation (MAD), and the tracking signal for these five months of forecasting?c. If the manager had used a 3-month moving average instead of her technique, what would have...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT