Solution:-

Overall equipment effectiveness = Availability * efficiency * Quality Output

Overall Equipment effectiveness = 0.93 * 0.97 *0.90

Overall Equipment effectiveness = 0.7509

Overall Equipment effectiveness = 75.09%

please like the answer........

Add a comment
Know the answer?
Add Answer to:
Calculate the overall equipment effectiveness for a copy machine that has an availability rate of 93%,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • OVERALL EQUIPMENT EFFICIENCY A CNC machine tool is used for single shift working, the machine tool...

    OVERALL EQUIPMENT EFFICIENCY A CNC machine tool is used for single shift working, the machine tool is operated for 8 hours per shift for 5 days per week. The CNC machine fool produces terminal blocks at a planned production rate of 60 units per hour Using the Availability, Performance and Quality losses given in the table below, (all values are in minutes per week) Calculate the average Overall Equipment Efficiency (OEE) for the machine tool over the three week period...

  • QUESTION 21 (10 points) ‐ Overall Equipment Effectiveness (OEE) QUESTION 21 (10 points) Overall Equipment Effectiveness...

    QUESTION 21 (10 points) ‐ Overall Equipment Effectiveness (OEE) QUESTION 21 (10 points) Overall Equipment Effectiveness (OEE) A copy machine is available 20 hours a day. On a typical day, the machine needs to process 360 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 30% of the jobs need to be reworked, in which the set-up time and the...

  • Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equ...

    Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equipment a typical Assembly plant for Availability Assumptions: At a typical plant, the constraint in the Widget production process is the machining line. The following information applies to the line for the week of June 5 through June 11. The line was schedulėd to run two &-bour shifts Monday through Friday, and one 9-hour shift on...

  • Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided...

    Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipped Actual run time this wook Machine time available per week Actual run note this week Ideal run rate Defect-free output this week Total output this week (including defects) 6,600 minutes 11,000 minutes 5.1 units per minute 6 units per minute 23,562 units 33,660...

  • 00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company...

    00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipood Actual run time this week Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (includine defects 7.500 minutes 12.see minutes 6.30 units per minute 7 units per minute 37,800 units...

  • A pipe bending machine used to produce ship system components was operated as follows: The period...

    A pipe bending machine used to produce ship system components was operated as follows: The period of operation was 25 days @ 10 hrs per day. It produced 800 total pipe details, of which 40 were rejected by quality inspectors. The total setup time for the machine during the 25 days was 22 hours. The machine had 3 unplanned breakdown events 1.5 hours for a power failure 0.5 hours for computer network failure 2.2 hours for lubricant pump failure The...

  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units actual run time this week! Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (including defects 4,900 minutes 7.003 minutes 3.8 units per minute 4.0 units per minute 15.827 units 18,620 units Book Required: 1....

  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 5.696 minutes 6,400 minutes 1.68 units per minute 2.00 units per minute 12,670 units 18,100 units Required: 1. Compute...

  • Copy equipment was acquired at the beginning of the year at a cost of $23,300 that...

    Copy equipment was acquired at the beginning of the year at a cost of $23,300 that has an estimated residual value of $2,100 and an estimated useful life of 5 years. It is estimated that the machine will output an estimated 1,060,000 copies. This year, 204,000 copies were made. a. Determine the depreciable cost. $ b. Determine the depreciation rate. per copy c. Determine the units-of-output depreciation for the year.

  • Copy equipment was acquired at the beginning of the year at a cost of $54,900 that...

    Copy equipment was acquired at the beginning of the year at a cost of $54,900 that has an estimated residual value of $5,000 and an estimated useful life of five years. It is estimated that the machine will output an estimated 998,000 copies. This year, 251,000 copies were made. Determine the (a) depreciable cost, (b) depreciation rate, and (c) units-of-activity depreciation for the year. Round "depreciation rate" to two decimal places. a. Depreciable cost $ b. Depreciation rate per copy...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT