E) Only (a) and (b) above 15. In project scheduling, when three time estimates are given for each activity i just one time es
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

15: Option B
The PERT Scheduling has the three types of times which are optimistic times, pessimistic times and mean times which are used to calculate the time estimates which are then used for the PERT calculation and scheduling. Hence Option B is correct.

17: Option A
Cause and effect diagram or fishbone diagram is generally used to understand the features which are most desired by the consumers of the product. This analysis is extremely crucial and widely used in product management by product managers. Hence, Option A

19: Option A
The Pareto chart is used to analyze the defects and their causes in quality management. It is used to calculate that 80% of the defects are due to 20% causes. Hence, the Pareto chart is used to determine defects and their probable cause. Hence, Option A

20: Option D
All the statements made are correct. The six sigma has 3.4 defects per million as per the initial findings of the two employees of Motorola who invented the six sigma approach. Six Sigma is intended towards reducing the waste from the processes and improve the quality of processes. Hence, Option D is correct.

Add a comment
Know the answer?
Add Answer to:
E) Only (a) and (b) above 15. In project scheduling, when three time estimates are given...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 29. A major difference between facilities planning and scheduling is that: A. Facilities planning...

    29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to long-range capacity plan and scheduling refers to short-range capacity plan. B. Facilities planning is concerned with allocating available resources and scheduling with the acquisition of resources. C. Facilities planning refers to medium-range resource requirement and scheduling refers to long-range capacity requirement. D. None of the above. 30. Suppose the cost of not having adequate capacity is very high. What type of capacity cushion strategy...

  • 29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to...

    29. A major difference between facilities planning and scheduling is that: A. Facilities planning refers to long-range capacity plan and scheduling refers to short-range capacity plan. B. Facilities planning is concerned with allocating available resources and scheduling with the acquisition of resources. C. Facilities planning refers to medium-range resource requirement and scheduling refers to long-range capacity requirement. D. None of the above. 30. Suppose the cost of not having adequate capacity is very high. What type of capacity cushion strategy...

  • 1. Facilities planning refers to: A. Medium-range capacity decisions B. Have no impact on other c...

    1. Facilities planning refers to: A. Medium-range capacity decisions B. Have no impact on other capacity decisions C. Are long-term in nature. D. Require planning for one year or less 2. Under exponential smoothing, if we want the forecast for the next period to be closer to current period actual demand, the value of alpha (a) should be: A. Large (close to 1.0) B. Small (close to zero) C. Zero D. The value of alpha will have no impact on...

  • 17. Cost of inspectors and testing are examples of: A. Prevention costs B. Appraisal costs C....

    17. Cost of inspectors and testing are examples of: A. Prevention costs B. Appraisal costs C. Internal failure costs D. External failure costs E. Improvement costs 18. Which of the following are reasons for the failure of quality improvement efforts in             organizations? A. Managers continue to focus on short-term financial results B. Managers instinctively blame employees when there is a quality failure C. Managers interfere with true teamwork D. All of the above E. Only A and B 19....

  • e) None of the above is true. Q#15. Which of the following statements is true? a)...

    e) None of the above is true. Q#15. Which of the following statements is true? a) Training of Service Personnel is a criterion for evaluating the explicit services feature of the service package. b) The fact that services are labor intensive ensures that the service is fair and equal for all customers. c) From a marketing perspective, services, unlike goods, involve transfer of ownership. d) Little or no interaction between customer and service provider is required when the service is...

  • Process of predicting a future event is known as Forecasting End casting Both A & B...

    Process of predicting a future event is known as Forecasting End casting Both A & B None of the above Short range forecasting time horizon is Up to 1 year, generally less than 3 months Purchasing, job scheduling, workforce levels, job assignments, production levels Both A & B None of the above Medium/long range forecasts deal with more comprehensive issues and support management decisions regarding planning and products, plants and processes True False Technological forecasts Address business cycle – inflation...

  • 9. A project manager spent some days to create a multi-page document, which he called project...

    9. A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor.The sponsor found the document outsized and asked for a condensed document. Which of the following is usually not an element of the project charter? a. The authority level of the project manager b. Detailed control account and work package descriptions C. The business need that the project was undertaken to address d. High-level...

  • 2. An American put option can be exercised: a. b. c. d. e. At any time...

    2. An American put option can be exercised: a. b. c. d. e. At any time on or before the expiration date. Only on the expiration date. Any time in the indefinite future. Only after the dividend has been paid. None of the above. 3. A European call option can be exercised: a. Any time in the future. b. Only on the expiration date. c. If the price of the underlying asset declines below the exercise price. d. Immediately after...

  • DO NOT ANSWER AT ALL IF YOU ARE ONLY ANSWERING 5 QUESTIONS THANK YOU True or...

    DO NOT ANSWER AT ALL IF YOU ARE ONLY ANSWERING 5 QUESTIONS THANK YOU True or false Process design includes selecting the appropriate technology, sizing the process over time, determining the role of inventory in the process, and locating the process. Operations and supply chain strategy is concerned with setting broad policies and plans for using the resources of a firm and must be integrated with corporate strategy. "Social" pertains to fair and beneficial business practices toward labour, the community,...

  • 1) If aggregate demand (AD) shifted to the right or left in the Keynesian zone, it...

    1) If aggregate demand (AD) shifted to the right or left in the Keynesian zone, it will determine the resulting level of ___________. Select the correct answer below: a) real GDP b) potential GDP c) output and unemployment d) inflationary price pressure 2) Long-run changes in aggregate supply, or the long-run aggregate supply curve, is defined by the vertical line at ____________. Select the two correct answers below. Select all that apply: a) full-employment GDP b) real GDP c) potential...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT