17. Cost of inspectors and testing are examples of: A. Prevention costs B. Appraisal costs C....

17. Cost of inspectors and testing are examples of:

A. Prevention costs

B. Appraisal costs

C. Internal failure costs

D. External failure costs

E. Improvement costs

18. Which of the following are reasons for the failure of quality improvement efforts in

            organizations?

A. Managers continue to focus on short-term financial results

B. Managers instinctively blame employees when there is a quality failure

C. Managers interfere with true teamwork

D. All of the above

E. Only A and B

19. How does the Malcolm Baldrige National Quality Award seek to strengthen US competitiveness in the global market?

A. By promoting better quality management practices in the US

B. By giving an award to selected US organizations to recognize their quality excellence

C. By publicizing quality achievements of U.S. companies

D. All of the above.

20. In quality improvement implementation, the Pareto chart is used:

A. to show the causes and effects of quality problems

B. to control proportion defective through quality control charts.   

C. to show the few but important problems that impact quality.
D. to show the upper and lower specification limits.


21. The Plan-Do-Check-Act (PDCA) cycle is a framework used in implementing the _____ process.
            A. process flow analysis

B. continuous improvement

C. new product design

D. None of the above.

22. Which of the following statements is true about six-sigma quality?

A. Requires no more than 3.4 defects per million parts.

B. Six-sigma is used to manage and control quality.

C. Six-sigma can be applied to manufacturing systems as well as to administrative

            and service processes

D. All of the above

E. Only (A) and (b) above.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

17. Answer is C. Internal failure costs

Since the inspectors and testing is merely ensuring faulty product does not reach the customers. No preventive measures are being taken.

18. Answer is D. All of the above

Managers failure to focus on long-term goals, take ownership of mistakes and incapability to entrust teamwork resulting in achieving quality improvement targets.

19. Answer is D. All of the above

This award is annually presented to those companies who exhibit high performance and quality.

20. Answer is C. to show the few but important problems that impact quality.

Pareto chart works on the principle of 80-20 i.e. 80% of problems arise from 20% of causes.

21. Answer is B. continuous improvement

PDCA cycle is a 4-step management method for continuous improvement.

22. Answer is D. All of the above

Six sigma methodolgy implies that 3.4 defects per million opportunities. This is applied for measuring and controlling quality of both manufacturing and service sectors.

Add a comment
Know the answer?
Add Answer to:
17. Cost of inspectors and testing are examples of: A. Prevention costs B. Appraisal costs C....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost of quality include(s) O a. external failure costs O b. internal failure costs O c....

    Cost of quality include(s) O a. external failure costs O b. internal failure costs O c. appraisal costs O d. all of the above Trends and emerging practices in project quality management include(s) O a. customer satisfaction b. continual improvement O c mutually beneficial partnerships with suppliers d. all of the above

  • Scrap and retesting are examples of ____ failure costs. a. external b. prevention c. appraisal d....

    Scrap and retesting are examples of ____ failure costs. a. external b. prevention c. appraisal d. internal e. detection

  • E) Only (a) and (b) above 15. In project scheduling, when three time estimates are given...

    E) Only (a) and (b) above 15. In project scheduling, when three time estimates are given for each activity i just one time estimate, the project scheduling method used is called: A) CPM B) PERT D) Kanban E) None of the above 16. With regard to time horizons in capacity planning, aggregate planning differs scheduling in that aggregate planning: A) is for the long-range and scheduling is for the short-range. B) is for the short-range and scheduling is for medium-range....

  • Past Paper (Q2) 1. What are examples of quality prevention, appraisal and failure costs. (5 marks)...

    Past Paper (Q2) 1. What are examples of quality prevention, appraisal and failure costs. (5 marks) 2. Discuss possible reasons for reducing project duration. Discuss the options that are available for accelerating project completion (5 marks) 3. Consider the following information. a. Draw the project network and determine the critical path for the network. (3 marks) b. Compute the duration that represents the lowest total project cost. (10 marks) c. What is this cost? (2 marks) (Note: You may find...

  • Pareto Chart and A report summarizing the costs, percent of total, and percent of sales by appraisal, prevention, internal failure, and external failure cost of quality categories.Cost of Quality Re...

    Pareto Chart and A report summarizing the costs, percent of total, and percent of sales by appraisal, prevention, internal failure, and external failure cost of quality categories.Cost of Quality Report for a Manufacturing Company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an The study of employee effort and other business records to determine the cost of activities.activity analysis to gain a better...

  • QUESTION 40 Appraisal costs refer to a. costs of reducing the potential for defects. b. costs...

    QUESTION 40 Appraisal costs refer to a. costs of reducing the potential for defects. b. costs of inspecting and evaluating products and/or services. c. costs caused by defective parts or products or by faulty service. d. all of these. e. none of these. QUESTION 41 An example of a service factory is a. mass media. b. mass transportation. c. fast food restaurants. d. all of the above. e. only a and b. QUESTION 42 Which one of the following distribution...

  • New York State Instructional Time Requirements : Q1-New York State requires at least 12.5 hours of instructional time (5...

    New York State Instructional Time Requirements : Q1-New York State requires at least 12.5 hours of instructional time (50 minutes equals 1 instructional hour) for each credit hour. Instructional time can consist of traditional in-class meetings as well as additional structured instructional activities (beyond usual homework, readings, and other preparation). In this 3-credit course, the required 37.5 hours consists of (i) 30 hours of in-class instruction, and (ii) 7.5 hours of online instructional activities. The on- line instructional activity will...

  • 1. Design costs are an example of: a) unit-level costs b) product-sustaining costs c) facility-sustaining costs...

    1. Design costs are an example of: a) unit-level costs b) product-sustaining costs c) facility-sustaining costs d) batch-level costs 2. A manufacturing firm produces multiple families of products requiring various combinations of different types of parts. Of the following, the MOST appropriate cost driver for assigning materials handling costs to the various products is: a) number of parts used b) number of suppliers involved c) number of units produced d) direct labor hours 3. A well-designed, activity-based cost system helps...

  • Multiple Choice/Matching -CIRCLE MULTIPLE CHOICE ANSWERS, NEATLY RECORD MATCHING 11. What are the three variables monitored...

    Multiple Choice/Matching -CIRCLE MULTIPLE CHOICE ANSWERS, NEATLY RECORD MATCHING 11. What are the three variables monitored in a quality control program? A. Accuracy, precision, and reliability B. Turnaround time, reliability, and reproducibility C. Reagent purity, specimen collection, and cost impact D. Avoiding trends, turnaround time, and cost impact 12. In performing routine quality control on a particular laboratory test, a high-quality control value is obtained that changes the mean. What type of change does this represent? A. Trend B. Standard...

  • 17. Direct costs: A. are incurred to benefit B. are incurred due to a spe C....

    17. Direct costs: A. are incurred to benefit B. are incurred due to a spe C. can be easily traced to D. are the variable Denefit a particular accounting period. due to a specific decision. traced to a particular cost object. sts of producing a product. 18. The main difference between van A. whether variable manufactum B. whether fixed manufacturing Cosu C. whether fixed manufact included in product costs. D. whether selling and en variable costing and absorption costing ufacturing...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT