Answers
Q.no.3
a) Rationale behind NPV Method :
Net present value method/technique is a discounted cash flow method that considers the time value of money in evaluating capital investment.
The NPV method use specified discount rate to bring all subsequent net cash inflows after the initial investment to the present values(the time of initial investment or year 0)
b) Under NPV method project which has highest postive NPV is accepted.
Q.no.4
Yes, NPV changes when WACC changes, because discount rate used to compute Present value of cash inflow will also change with cahnge in WACC.Hence there will be change in present value of cash inflow that effect NPV of the project
Answers
Q.no.3
a) Rationale behind NPV Method :
Net present value method/technique is a discounted cash flow method that considers the time value of money in evaluating capital investment.
The NPV method use specified discount rate to bring all subsequent net cash inflows after the initial investment to the present values(the time of initial investment or year 0)
b) Under NPV method project which has highest postive NPV is accepted.
Q.no.4
Yes, NPV changes when WACC changes, because discount rate used to compute Present value of cash inflow will also change with cahnge in WACC.Hence there will be change in present value of cash inflow that effect NPV of the project
3) What is the rationale behind the NPV method? According to NPV, which project or projects...
If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...
1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...
NPV Your division is considering two projects with the following cash flows millions): Project A 19 Project B 17 a. what are the wojects' Nns assuming the wACC is 5%? Round your answer to two decimal places Do not round your intermediate oalculatio s Enter your ans w $8 $11 $15 $8 s6 maons. .。 example, an answer of $10,50,000 should be entered as 10.5s. Negative value should be indicated by a minus sign Project A Project 8s what are...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is...
NPV Your division is considering two projects with the following cash flows (in millions): 1 3 $8 $8 $3 Project A -$17 -$26 $9 Project B $13 $10 a. What are the projects' NPVS assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A million...
NPV Your division is considering two projects with the following cash flows (in millions): Project A -$11 $4 $7 Project B $20 $12 a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $ .02 million Project B $...
1a. Why might a financial analyst use the NPV method for making project decisions instead of the IRR method? ------------------ 1b. Explain the reinvestment rate assumption in the context of a project’s cash flows over time. ------------------ 1c. When we create NPV profiles, what variable is on the y-axis and what variable is on the x-axis? ------------------ 1d. Suppose a firm’s WACC exceeds the IRR for both projects L and S, if the projects are mutually exclusive, which project should...
s NPV Your division is considering two projects with the following cash flows (in millions): o 1 2 3 + Project -$35 $4 $14 $20 A Project -$15 $a $5 $1 B a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus...
NPV Your division is considering two projects with the following cash flows (in millions): 0 2 3 Project A Project B $29 -$16 $15 $8 $13 $3 $3 $6 a. what are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ Project B $ what are the projects' NPVs assuming the WACC is 10%? Round...
1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...