Question

One reason for crashing a project is: Market needs change and the project is not in...

One reason for crashing a project is:

Market needs change and the project is not in demand any more.

The project has slipped behind schedule.

There are no repercussions for delivering the project late.

That the initial schedule may be too pessimistic.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  • The project has slipped behind schedule

Delays that occur in the initial stages or in the middle of a project have an impact on the subsequent tasks and final delivery date. In such a situation, project crashing can be implemented to compensate for the lost time.

Crashing in project management aims to reduce the duration of the project. It requires additional investments and hence it is implemented only in the case of an emergency and after considering all the possible alternatives.

Add a comment
Know the answer?
Add Answer to:
One reason for crashing a project is: Market needs change and the project is not in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Concrete is one input the government needs to complete a public infrastructure project. The concrete market...

    Concrete is one input the government needs to complete a public infrastructure project. The concrete market is effectively a monopoly. Use the diagram below, showing the effects of government purchasing in the concrete market, to answer the following questions. Do is the private sector demand for concrete and D, is the augmented demand curve reflecting both private sector demand and government purchases, MC BP 0,0,0, MR Indicate the areas that represent the impact to consumer surplus (i.e. change in CS)...

  • You just completed developing the schedule for your project and got the approval from stakeholders and...

    You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will...

  • DEMAND. SUPPLY, AND MARKET EQUILIBRIUM KEY TERMS change in demand change in quantity demanded change in...

    DEMAND. SUPPLY, AND MARKET EQUILIBRIUM KEY TERMS change in demand change in quantity demanded change in quantity supplied change in supply complements demand schedule excess demand (shortage) excess supply (surplus) individual demand curve Individual supply curve Inferior good law of demand law of supply market demand curve market equilibrium market supply curve minimum supply price normal good perfectly competitive market quantity demanded quantity supplied substitutes supply schedule EXERCISES All problems are assignable in MyEconLab The Demand Curve Describe and explain...

  • Consider a project with free cash flow in one year of $130,000 in a weak market...

    Consider a project with free cash flow in one year of $130,000 in a weak market or $180,000 in a strong market, with each outcome being equally likely. The initial investment required for the project is $100,000, and the project's unlevered cost of capital is 20%. The risk-free interest rate is 10%. (Assume no taxes or distress costs.) a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...

  • Consider a project with free cash flow in one year of $130,000 in a weak market...

    Consider a project with free cash flow in one year of $130,000 in a weak market or $180,000 in a strong market, with each outcome being equally likely. The initial investment required for the project is $100,000, and the project's unlevered cost of capital is 20%. The risk-free interest rate is 10%. (Assume no taxes or distress costs. a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...

  • Consider a project with free cash flows in one year of $132,459 in a weak market...

    Consider a project with free cash flows in one year of $132,459 in a weak market or $193,776 in a strong market, with each outcome being equally likely. The initial investment required for the project is $60,000, and the project's unlevered cost of capital is 22%. The risk-free interest rate is 3%. (Assume no taxes or distress costs.) a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...

  • Consider a project with free cash flows in one year of $133,605 in a weak market or $196,786 in a...

    Consider a project with free cash flows in one year of $133,605 in a weak market or $196,786 in a strong​ market, with each outcome being equally likely. The initial investment required for the project is $65,000​, and the​ project's unlevered cost of capital is 24%. The​ risk-free interest rate is 9%. ​(Assume no taxes or distress​ costs.) a. What is the NPV of this​ project? The NPV is ​$ _____? b. Suppose that to raise the funds for the...

  • What is the importance of the project scope? According to the textbook, the project scope is,...

    What is the importance of the project scope? According to the textbook, the project scope is, “The work that needs to be accomplished to create the project deliverables.” It is one of the first steps in managing a project, and it is also one of the most important because it involves the project requirements and boundaries. Based on the lessen for this week, the scope defines the boundaries of the project, the estimated time it will take to complete the...

  • Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that...

    Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that there is a sample for filling the reason column please see it. Risk Probability Effects Reason Organizational financial problems force reductions in the project budget (7). Low Catastrophic It is impossible to recruit staff with the skills required for the project (3). High Catastrophic Key staff are ill at critical times in the project (4). Moderate Serious Faults in reusable software components have to...

  • 1)To meet market needs companies sometimes change product names so that the name in the local...

    1)To meet market needs companies sometimes change product names so that the name in the local language is culturally meaningful. This is an example of a company using ________ strategy. A) an international B) a multidomestic C) a single country D) a transnational 2)Panasonic entered the market in China and found that it needed to balance global integration with local adaptation. It set up a Lifestyle Research Center in China to interpret data on customer wants and needs. This is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT