Question

Create a Gantt Chart with EXCEL and show all steps.

Activity Preceding Activity Duration (Weeks) C,D E,F C,D G,J,K

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Dur EF= ES+Dur
Task Pre Duration ES EF Critical LS LF End Slack
a ------ 2 0 2 Yes 0 2 0
b ------ 2 0 2 Yes 0 2 0
c a, b 4 2 6 Yes 2 6 0
d c 3 6 9 Yes 6 9 0
e a, b, c 1 6 7 8 9 2
f d, e 2 9 11 Yes 9 11 0
g f 3 11 14 Yes 11 14 0
h g 1 14 15 Yes 14 15 0
Project duration (Max of EF) 15

22431231 2269 9 14 00268914 4 ab cd ef gh 0

B.

So we assume weekend days are included in time if they come on from 5 to 7, 12 to 14, 19 to 21 etc.

Including weekends
Start End Time Weekends days
a 0 2 2 0
b 0 2 2 0
c 2 8 6 2
d 8 11 3 0
e 11 12 1 0
f 12 16 4 2
g 16 19 3 0
h 19 22 3 2

Including weekends Start End Weekends days Time 2 2 12 16 19 16 19 10 15 25 Time

Add a comment
Know the answer?
Add Answer to:
Create a Gantt Chart with EXCEL and show all steps. Activity Preceding Activity Duration (Weeks) C,D...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • : A network consists of the following list. Times are given in weeks. Activity Preceding Duration...

    : A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...

  • Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a...

    Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...

  • Draw an Gantt chart using the following figure. Duration (Days) Preceded by Activity B 22 10...

    Draw an Gantt chart using the following figure. Duration (Days) Preceded by Activity B 22 10 13 8 15 Immediately Following Activities DJ CF DJ -- C, F, G H, I, K HI, K DJ BE A, C, H F 17 ewuQIM 15 11 22

  • Calculate the expected project completion time (in weeks) using a Gantt chart and the international convention....

    Calculate the expected project completion time (in weeks) using a Gantt chart and the international convention. Then, write the exact date of the completion of this project using the Official International Standard. ANSWER ONLY IF YOU KNOW THESE TWO QUESTIONS! A) Duration of the project (IN WEEKS) B) Exact completion data using the OFFICIAL INTERNATIONAL STANDARD Activity DurationPredecessorsStart Date 2019-04-01 A,B D, E F,G

  • Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1...

    Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1 A E 6 A F 3 D G 3 C,E a. Construct a network diagram showing the critical path. b. Identify the earliest time the campaign can start. c. Identify the activities where there is float/slack time in the project, and calculate how much float/slack time there is. ** You should show all of your workings and state, clearly, any assumptions made.                                              

  • PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! PLEASE SHOW ALL WORK...

    PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! HW 4- All work must be completed in 1 excel file that, when necessary, includes cells that make calculations. 1) Information on a project's activities is shown in the following table ctivity Immediate Predecessor Activity Time (wks) Total Budgeted Cost 25,000 4 28,000 16,000 10 44,000 36,000 B, D, E 55,000 B, D, E 80,000 21,000...

  • Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c,...

    Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g d 5 h f,g 8 Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points...

  • 1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C...

    1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C A 3 D A 2 E B 3 F C 6 G C, D 5 H E, F 6 I G 5 J H, I 5 Activities B and H can be shortened by a minimum of 2 time units. Which activity would you shorten to reduce the project duration of 2 weeks. Why? (be specific)

  • 1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity...

    1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. Redesign 13. Demonstrate solution to class 2,3 2 8 10 11 12

  • Concerning the activities the following standards were set: ACTIVITY DESCRIPTION PRECEDING ACTIVITY ACTIVITY DURATION(DAYS) A Feasibility...

    Concerning the activities the following standards were set: ACTIVITY DESCRIPTION PRECEDING ACTIVITY ACTIVITY DURATION(DAYS) A Feasibility Study None 7 B Internal Specs A 5 C External Specs A 13 D Internal Analysis B 5 E Functional Specs C,D 10 F Hardware Specs E 15 G Hardware Acquisition F 5 H System Installation G 3 I Design material A 45 J System Testing H,I 10 a) Draw a network diagram (Activity-on-None) of the project presented in the case study with all...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT