Calculate the expected project completion time (in weeks) using a Gantt chart and the international convention.
Then, write the exact date of the completion of this project using the Official International Standard.
ANSWER ONLY IF YOU KNOW THESE TWO QUESTIONS!
A) Duration of the project (IN WEEKS)
B) Exact completion data using the OFFICIAL INTERNATIONAL STANDARD
Solution : End Date : 2019-07-29
Calculate the expected project completion time (in weeks) using a Gantt chart and the international convention....
Create a Gantt Chart with EXCEL and show all steps. Activity Preceding Activity Duration (Weeks) C,D E,F C,D G,J,K
If a project has an expected time of completion Te of 45 weeks with a standard deviation of 7 weeks, what is the probability of completing it (a) within one year (52 weeks)? (b) within 38 weeks. Please solve the problem using PERT , Optimistic time, most likely time, and pessimistic time. Using this formula : Te = (a+ 4M+ b) / 6
Draw an Gantt chart using the following figure. Duration (Days) Preceded by Activity B 22 10 13 8 15 Immediately Following Activities DJ CF DJ -- C, F, G H, I, K HI, K DJ BE A, C, H F 17 ewuQIM 15 11 22
Using Table 2.13 below, if the expected time for activity E is changed to nine weeks, by how many weeks will the project's expected completion time increase? Table 2.13 (All activity times for the project are in weeks.) Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessors(s) A 3 4 5 --- B 5 7 9 --- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 CD G 7...
Chapter - Project Management This assignment involves creating a Gantt chart using the GanttProject software. 1) Use the attached example task list to create a new Gantt chart. Make sure you indicate the task dependencies from the task list. Use the IDs assigned by the site, not the ones in the example. 2) Add two new tasks: the 1st between "Programming" and "Program Test" called "Code Review" with duration 3 days, and the 2nd between “Write User Manual” and “User...
3. (20 points) A landscaping upgrade project consists of following activities. Times are given in weeks. Activity | Immediate Predecessor Activity Time A А ထင်ထ F B, DC D D 3 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity b. Construct an early-start-date Gantt chart for the project. C. As a project manager, where would you focus your attention, given your analysis?
1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. Redesign 13. Demonstrate solution to class 2,3 2 8 10 11 12
a. Develop a report that presents a planned schedule and expected project completion time in workdays. Include a project network in your report using MS Project. b. Explain how does this project compared to the average project. The average duration for a construction of a villa project normally takes 120 workdays. c. Find the probability of finishing this project in 120 workdays? d. Also find what expected completion time will ensure a 90% chance of completing the project in 120...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...