Question
Chapter - Project Management

This assignment involves creating a Gantt chart using the GanttProject software.

1) Use the attached example task list to create a new Gantt chart. Make sure you indicate the task dependencies from the task list. Use the IDs assigned by the site, not the ones in the example.

2) Add two new tasks: the 1st between "Programming" and "Program Test" called "Code Review" with duration 3 days, and the 2nd between “Write User Manual” and “User Training” called “User Manual Review” with duration 2 days.

3) Identify all the tasks in the critical path for the project by coloring those items red.

4) Export your Gantt file (.gan) from GanttProject .
Assign Tasks Program Test System Test ID: 2 D:4 ID: 6 ID:9 Dur:4 Dur: 70 Dur: 30 Dur: 25 Develop Plan User Test Write User Manual Dur: 1 Dur:25 ID: 7 Dur: 25 Obtain Hardware Install Hardware User Training ID:3 D: 5 ID: 10 Dur: 17 Dur: 10 Convert Fles Dur: 20 ID: 8 Dur: 20
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Grantt Chart ,Tasks and Task ids

To change colour of criticl path before starting the project configurations must be done so please try to configure first before starting project.

Ganttproject is very easy tool to create charts. c

Add a comment
Know the answer?
Add Answer to:
Chapter - Project Management This assignment involves creating a Gantt chart using the GanttProject software. 1)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a...

    Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...

  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • 1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity...

    1. Using Microsoft Excel prepare a Gantt Chart for the following project. Predecessor(s) Duration (Days) Activity 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. Redesign 13. Demonstrate solution to class 2,3 2 8 10 11 12

  • al Industries are likely to use 4 At Webster University, where you work as a project...

    al Industries are likely to use 4 At Webster University, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): . First, confirm arrangements for the training facility you plan to use (2 days). • After you have confirmed the training facility, two tasks can begin at the same time:...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • You could consider each week of a course as a small project. It requires you to...

    You could consider each week of a course as a small project. It requires you to study some learning resources, participate in a discussion, and possibly complete a paper or a test. Create a work breakdown structure (WBS) that represents your projects for this week. Document the tasks you were asked to perform in this week of the course (you can use the list above as a starting point). Decompose each main task into subtasks that can be completed in...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • Please Implement this code using Java Eclipse. CIS 1068 Assignment 8 Warm Up with Objects Due:...

    Please Implement this code using Java Eclipse. CIS 1068 Assignment 8 Warm Up with Objects Due: Wednesday, March 25 70 points (+ up to 15 extra credit) The purpose of this assignment is to give you practice implementing your own classes. It also provides extra practice with arrays. Task Implement a class Task, which is used to represent a job that should be done. It should contain the following private fields: .name text description of what job should be done...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT