Question

You are in charge of transportation of a product for company A. The company has three production facilities across the state of Georgia, and two cross-docks that receive product from each of the production facilities and then distribute it to three retail stores. Every production facility can send their product to either cross-dock, but cross-dock 1 can only satisfy the demand of retailers 1 and 2, while cross-dock 2 can satisfy the demand of retailers 2 and 3. Table 1 shows the production capacity of each production facility over the planning horizon of four weeks, and Table 2 shows the demand of each retailer for the planning horizon. Retailers demand must be met on time without backlogging.

Period Facility Facility 4. 2 4 P1500 420 470 450 P2850 780 740 820 P3400 450 430 480 R1 420 490 420 470 R2710 820 720 790 R3

The figure below shows the layout of the company’s network:

P1 R1 CD 1 P2 R2 CD 2 P3 R3   

     Capacity Cost Capacity Cost 500 280 600 300 650320 650 450 Arc Arc (P1,CD1) 400 250(CD1, R1) (P1,CD2)350 300(CD1, R2) (P2,CD1

Product is sent by truck between facilities with each pair of facilities having different capacities and transportation cost per unit of product. Table 3 show the capacity and cost for each facility pair in the network; these are the same for each week in the planning horizon.

Model this problem as a minimum cost network flow problem. In your network, nodes should represent facility-week combinations so you can track flows at different points in the horizon.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost As A Priority

Jocelyn would like to apply at MGM Manufacturing to become their transportation manager. She's heard that they prefer to use the minimum cost method for solving their transportation problems, but she hasn't had an opportunity to use that method at her current position. She seeks help from Bill a former colleague who she knows has used it. Let's listen in:

Bill says: Well, Jocelyn, the minimum cost method, sometimes called the minimum cell cost method or least cost method is used when the priority is to reduce costs for distribution of materials. As you know, you can use other methods if the priority is time savings rather than cost savings. But it looks like MGM Manufacturing wants to distribute their product for as little cost as possible, thus reducing the overall cost of the product. Let's look at a problem I had just last week.

Constraints

In the case of the recent problem I had, there were six constraints, three from the supplier and three from the destination. Constraints are the limitations of the distribution such as how much a factory can supply and how much of the product a given facility needs. Let's take a look at the constraints for my transportation problem:

Supply constraints:

  • Orlando supplier can produce fifteen truckloads of the product.
  • Baltimore supplier can produce thirty truckloads of the product.
  • Boston supplier can produce twenty truckloads of the product.

Destination constraints:

  • Las Vegas needs five truckloads
  • Seattle needs twenty truckloads
  • St. Louis needs forty truckloads

I created a transportation matrix which is just a simple table that shows all constraints:

Destinations Las Vegas Seattle St. Louis Supply Orlando Baltimore Boston 15 30 20 Demand 5 20 40

Cost Information

Once I knew my constraints, I gathered information on the cost for delivery from each supplier to each destination and added that to my matrix (in red):

Destinations 15 45 30 Las Vegas Seattle St. Louis Supply 35 60 20 15 30 20 n Orlando Baltimore Boston 60 30 90 Demand 20 40

Now that I have all the information in my matrix, I can solve the transportation problem using the least cost or minimum cost method.

Solve the Problem

I start out by looking for the cell with the lowest cost for transportation. In this case, it's the route from Orlando to Las Vegas at a cost of fifteen, so I want to fill as much of the Las Vegas demand with my supply from Orlando. Orlando can supply fifteen but Las Vegas only needs five, so I fill that in (in blue) and cross out the demand for Las Vegas:

Destinations Las Vegas Seattle St. Louis Supply Orlando 15 5 60 30 90 35 60 20 15 30 20 Baltimore 45 Boston 30 Demand 5 20 40

Now I go on to the next lowest cost which is the Boston to St. Louis route for a cost of twenty. Boston can supply twenty but St. Louis needs forty, so I will assign all of Boston's supply to St. Louis which crosses out Boston's supply:

Destinations Las Vegas Seattle St. Louis Supply Orlando15 5 60 35 Batimore 45 Boston 15 30 60 30 30 90 20 20 20 Demand s 20 4

I continue in the same manner, looking for each cell that is the least expensive and assign as much as I can from the supplier to meet the demand of the destination.

Both the Boston to Las Vegas and the Baltimore to Seattle routes have a cost of thirty, but the Las Vegas demand has already been filled, so I can move directly to the Baltimore/Seattle route. Seattle needs twenty and Baltimore has thirty so I fill the Seattle demand from Baltimore and cross out the Seattle demand:

Add a comment
Know the answer?
Add Answer to:
You are in charge of transportation of a product for company A. The company has three...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 7-11 (Algorithmic) Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments:...

    Problem 7-11 (Algorithmic) Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Product 1 Product 2 Product 3 A 1.60 3.10 2.10 B 2.20 1.20 2.70 C 0.35 0.35 0.35 During the next production period, the labor-hours available are 470 in department A, 370 in department B, and 70 in department C. The profit contributions per unit are $27 for product 1, $30...

  • Hart Manufacturing makes three products. Each product requires manufacturing operations in three ...

    Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Product 1 Product 2 Product 3 A 2.00 1.50 3.00 B 2.50 2.00 1.00 C 0.25 0.25 0.25 During the next production period the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $30 for product 1, $25 for product 2,...

  • ABC distribution does delayed differentiation of products for a customer at its distribution facility. The forecasted...

    ABC distribution does delayed differentiation of products for a customer at its distribution facility. The forecasted demand for one of these products during the next five months is 420, 580, 310, 450 and 540 400 respectively. The per unit costs and the capacity availability for producing these items are given below.                                                              Month                               1             2               3             4             5 Customization Cost   $24              $40               $36        $54        $60 Capacity                       500             520               450        550        400 The inventory costs is $0.55 per month for...

  • Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Pro...

    Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Product 1 Product 2 Product 3 A 2.00 1.50 3.00 B 2.50 2.00 1.00 C 0.25 0.25 0.25 During the next production period the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $30 for product 1, $25 for product 2,...

  • The following information relates to a joint production process for three products, with a total joint...

    The following information relates to a joint production process for three products, with a total joint production cost of $155,000. There are no separable processing costs for any of the three products. Product/ Sales Value of split off Units at Split-Off 1 $ 217,000 450     2 46,500 1,050 3 46,500 1,500 $ 310,000 3,000 What percentage of joint cost is allocated to each of the three products using the sales value at split-off method? P1: %, P2: %, P3:...

  • Please, someone walk me through this :) Davy Company has three products. Product 1 is manufactured...

    Please, someone walk me through this :) Davy Company has three products. Product 1 is manufactured entirely in Department P1. Product 2 is manufactured entirely in Department P2. Product 3 is manufactured entirely in Department P3. To produce these products, Davy has three support departments: S1 (materials handling), S2 (milling), and S3 (power). Davy is considering buying its power from an external supplier for $110.00 per kilowatt-hour (KWH). The budgeted variable costs and the allocation bases for each support department...

  • The Blair Company’s three assembly plants are located in California, Georgia, and New Jersey.  Previously, the company...

    The Blair Company’s three assembly plants are located in California, Georgia, and New Jersey.  Previously, the company purchased a major subassembly, which becomes part of the final product, from an outside firm.  Blair has decided to manufacture the subassemblies within the company and must now consider whether to rent one centrally located facility (e.g. in Missouri, where all subassemblies would be manufactured) or to rent three separate facilities, each located near one of the assembly plants, where each facility would manufacture only...

  • Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Pro...

    Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Product 1 Product 2 Product 3 A 2.00 1.50 3.00 B 2.50 2.00 1.00 C 0.25 0.25 0.25 During the next production period the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $30 for product 1, $25 for product 2,...

  • A Kensington Company is planning production for the next 4 quarters. They want to minimize the...

    A Kensington Company is planning production for the next 4 quarters. They want to minimize the cost of production. The production cost is stable but demand and production capacity vary from quarter to quarter. The maximum amount of inventory which can be held is 12,000 units and management wants to keep at least 3,000 units on hand. Quarterly inventory holding cost is 3% of the cost of production. The company estimates the number of units carried in inventory each month...

  • A company has three production plants P1, P2, P3. In each of these plants, three A, B, C products...

    A company has three production plants P1, P2, P3. In each of these plants, three A, B, C products are manufactured. Suppose that from an input unit it is known that: The first plant produces 4 units of A; 2 of B and 4 of C; the second plant produces 5 units of A; 4 of B and 2 of C; the third plant produces 2 units of A; 4 of B and 5 of C. The claims to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT