A company makes two products in a single plant. It runs this plant for 100 hours each week. Each unit of product A that the c

IGNORE THE BLUE DOT:

A. It will stay the same

B. 500

C. 850

D.1250

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Decision variables:

A = units of product A that the company produces per week

B = units of product B that the company produces per week

Objective Function:

Max 1000 A + 2000 B (profit $/week)

Constraints:

• Restrictions on production

2A + B ≤ 100

• Restrictions on emission

4A + 3B ≤ 240 B ≤ 60

• Nonnegativity constraint on each of the two variables.

A ≥ 0, B ≥ 0

OBJECTIVE FUNCTION VALUE

1) 135000.0

VARIABLE     VALUE REDUCED          COST

       A                 15.000000             0.000000

       B                  60.000000             0.000000

ROW             SLACK OR SURPLUS      DUAL PRICES

2)                         10.000000                 0.000000

3)                          0.000000                250.000000

4)                          0.000000              1250.000000

NO. ITERATIONS= 2

The optimal plan is to produce each week 15 units of product A and 60 units of product B

Reducing the production hour by 10 hours, the plant’s profit will drop by an amount of $1250.

The correct option is D.

Add a comment
Know the answer?
Add Answer to:
IGNORE THE BLUE DOT: A. It will stay the same B. 500 C. 850 D.1250 A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 2 Linear Programming 1.         The Scrod Manufacturing Co. produces two key items – special-purpose Widgets...

    Exercise 2 Linear Programming 1.         The Scrod Manufacturing Co. produces two key items – special-purpose Widgets (W) and more generally useful Frami (F). Management wishes to determine that mix of W & F which will maximize total Profits (P). Data                                                                      W      F             Unit profit contributions                     $ 30   $ 20             Demand estimates (unit/week)               250      500             Average processing rates – each product requires processing on both machines (units/hour)                                     Machine #1                        2          4                                        Machine #2                ...

  • QUESTION 3 The textbook discusses 3 types of environmental degradation affecting the environment. Below, please match...

    QUESTION 3 The textbook discusses 3 types of environmental degradation affecting the environment. Below, please match each type of degradation discussed to the type of consequence suggested in the textbook. (Answer based on what the book says, not based on your personal opinion.) Air pollution A., is killinig humans 8,..isklin the earth Land poliution Water pollution address chiticar Watel Air Pollution Air pollution occurs when the release of materials to the atmosphere cannot be safelv disposed of by natural processes....

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT