Question
Please do problem #2. I posted both problems 1 and 2 because problem 2 is based on problem 1. Please do part a,b and c. Label each part clearly

(5 points) Given below are the cost curves of 5 generators which are to supply a load of 750 MW: 1. fi -0.01 Pa2+2 Pa+50 f 0.005 P24 P2 +200 f 0.0075 P+1.5 Pe3 +10 S/h f4-0.04 Pgs 0.5 P4+ 150 fs-0.003 P +3 Pgs+ 12S/h S/h S/h S/h Assume that the cost curve coefficient units are a,- S/Mw*h, b,- S/MWh, c S/h. a. Find the incremental fuel cost equation (in S/MWh) for each generator. b. Neglecting system losses (and generator limits), determine the optimal dispatch of each generator (i.e. Pgl, P2, etc.). Find the total cost (i.e fit ft.) of the generation schedule from Part b. c. 2. (5 points) Now assume that each generator in Problem 1 has the following active power generation constraints. 100 s Pp S 500 MW 50 s P 300 MW 25 s Pet S 200 MW 50 Ps150 Mw Find the optimal dispatch of each generator that satisfies the active power generation limits a. b. Find the total operating cost of the generation schedule in Part A c. Calculate the change in operating cost compared to your answer in Problem 1(c). Does enforcing generator limits result in cost savings or a cost increase? Is this what you expected? Why?
0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Please do problem #2. I posted both problems 1 and 2 because problem 2 is based...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Problem 2 The fuel-cost function in $/h of two thermal plants are ?1 = 320 +...

    Problem 2 The fuel-cost function in $/h of two thermal plants are ?1 = 320 + 6.2?1 + 0.004?1 2 , ?2 = 200 + 6.0?2 + 0.003?2 2 , where ?1 and ?2 are in MW. Plant outputs are subject to the following limits (in MW) Problem 2 The fuel-cost function in $/h of two thermal plants are C1 = 320 +6.2P2 +0.004P], C2 = 200 +6.0P2 + 0.003P2, where P and P2 are in MW. Plant outputs are...

  • Economic Operation and control of PS 2. Find the optimal dispatch and the total cost in...

    Economic Operation and control of PS 2. Find the optimal dispatch and the total cost in $/h for the thermal plants in problem 1 when the total load is 1000 MW with the following generator limits (in MW): 200SP 5455; 1505PX350; 1005Px5250. chine 1. The fuel-cost functions for three thermal plants in S/h are given by G=600 +5.4P +0.004P,?: C500 5.6P2 +0.006P2?; C = 300 + 5.9P+0.009P3 Where P. P. and P, are in MW. The total load, Po, is...

  • Power economic schedule, economic dispatch question Problem 02) The system to be studied consists of two...

    Power economic schedule, economic dispatch question Problem 02) The system to be studied consists of two units as described as follows. Assume that the fuel inputs in MBtu per hour for units 1 and 2, which are both on-line, are given by H = 8P+0.024P2 + 80 H, = 6P, +0.04P + 120 Where, H = fuel input to unitn in MBtu per hour (millions of Btu per hour) (n = 1,2) Pr = unit output in megawatts (n =...

  • Three generators supply a load centre with a demand Pd. The aim is to dispatch them...

    Three generators supply a load centre with a demand Pd. The aim is to dispatch them so that the total cost of generation is minimised. The generators have the following cost functions: Ci(Pi) = 600 + 10P1 +0.016P[$/hour] C2 (P2) = 500 +8P2 +0.018P2 $ /hour) C3 (P3) = 700 + 12P3 + 0.018P} [$/hour] and the following technical limits: PL € (100 MW, 400 MW] P2 € [150 MW, 500 MW] P3 € (50 MW, 300 MW] Your task...

  • 4.4 You are given three generating units and asked to find the optimal unit commit- ment...

    4.4 You are given three generating units and asked to find the optimal unit commit- ment schedule for the units to supply load over a 4-h time period. our MW Load 400 1000 1600 400 Gen 1: F(P) 2200+25P 0.025xP2 where 220s P, s600 MW Gen 2: F2(P)1500+P +0.02 x P2 where 350sP2s800MW Gen 3: F, B-l 000 + 20P, + 0.0 1 5 × P where 150 P, 600 Each generator has a start-up cost that must be factored...

  • Problem 2 -The fuel-cost curves for a three-generator po system are given as follows: Ax10 P...

    Problem 2 -The fuel-cost curves for a three-generator po system are given as follows: Ax10 P C2(P2)-600+ 10xP2+0.3 xP2 Ca(Ps)900+ 15xP3+0.1x P, The system losses in MW can be approximated as: P 10 If the system is operating with a marginal cost(λ) of $50/hr, dete (a) The output of each unit, (b) The total transmission losses cost (A) of SSO/hr, determin10% Pf+ 10% P3, 4x104 P1 P2 (c) The total load demand, (d) The total operating cost.

  • The solution to the problems includes detailed explanation, presentation and discussion of results. It is recommended...

    The solution to the problems includes detailed explanation, presentation and discussion of results. It is recommended to solve the problem through GAMS, Matlab, etc. PROBLEMS 5.1 Three units are on-line all 720h of a 30-day month. Their characteristics are as follows: H, = 225+8.47P, +0.0025P,?, 50 SP, S 350 H, = 729+6.20P, +0.0081P2, 50 5 P, S 350 H, = 400+ 7.20P, +0.0025P², 50 P, S 450 In these equations, the H. are in MBtu/h and the P. are in...

  • a) Formulate a cost function along with constraints, if any, for the following optimization problems. You don't nee...

    a) Formulate a cost function along with constraints, if any, for the following optimization problems. You don't need to solve any of these problems i) Two electric generators are interconnected to provide total power to meet the load. Suppose each generator's cost (C) is a function of its power output P (in terms of units), and costs per unit are given by: C2 = 1 + 0.6P2 + P22 (for Generator 2). -1-P -Pi2 (for Generator 1), If the total...

  • The six-bus system shown in Figure 1 will be simulated using MATLAB. Transmission line data and b...

    The six-bus system shown in Figure 1 will be simulated using MATLAB. Transmission line data and bus data are given in Tables 1 and 2 respectively. The transmission line data are calculated on 100 MVA base and 230 (line-to-line) kV base for generator. Tasks: 1. Determine the network admittance matrix Y 2. Find the load flow solution using Gauss-Seidel/Newton Raphson method until first iteration by manual calculation. Use Maltab software to solve power flow problem using Gauss-Seidel method. Find the...

  • Problem 5: Product Differentiation in a Bertrand Setting. Firms 1 and 2 face the same AC...

    Problem 5: Product Differentiation in a Bertrand Setting. Firms 1 and 2 face the same AC = MC = 30 but sell differentiated products. The demands for firms 1 and 2 are given by D.(P1, P2) = 70 – P1 + P2 D2(P1, P2) = 70 – P2 +5 P1 The firms choose prices Pı and P2 simultaneously. a) For each firm, represent profits as a function of both prices p and p2. b) Find the best response function for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT