The formula to calculate the expected time of an activity = (O+4M+P)/6.
Where, O = optimistic time
M = Most likely time
P = Pessimistic time
So using the above formula, the expected completion time of each activity are
Now the various paths and their expected completion time of the project are
So the critical path is A-B-D-E as it has the longest expected completion time of 38
Expected completion time of the project = Completion time of the critical path = 38
So the answer is 38
Question 7 Activity Of isti Te Mest IketTe Pesi istic Tre Predecessar A 7 10 13...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three-time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project is completed in 31 days? Activity Optimistic time Most Likely time Pessimistic time Predecessor Corner Posts 4 5 6...
QUESTION 1: TURN THIS GNATT CHART INTO AN ACTIVITY TABLE. FOR EXAMPLE THE TABLE SHOULD BE FORMATED LIKE THIS BUT MATCH THE DATA OF THE GNATT CHART BELOW, (THIS IS THE EXAMPLE OF A ACTIVITY TABLE FORMAT NOT THE SAME DATA AS THE GNATT CHART) ONCE AGAIN, QUESTION IS TO CONVERT THE DATA IN THE GNATT CHART INTO ITS' ACTIVITY TABLE (ACTIVITY NO., ACTIVITY, TIME (WEEKS), IMMEDIATE PREDECESSORS..) Activity No. Activity Time (weeks) Immediate Predecessors Collect requirements Analyze processes Analyze...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Hilf mir.9) Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. ( F 3 B 8 А G 6 5 с 11 H 6 4 9 A) 13 B) 21 C) 8 D) 14 10) What is the early start time for activity C if it has the start to start relationship shown? ( 20 A 27 25 B 29 ?? C 30 30 D 42 4 ?? 12 WA...
can you help me wirh this question please Question 7 1 pts 5- Draw the activity-on-node project network associated with the following activities for a construction project. How long should it take the team to complete this project? What are the critical path activities? Provide your answers in the blank fields below. Immediate Predecessor(s) Time (Days) Activity IA 3 B A 4 IC с A 6 D B 6 E B 4 IF c с 4 G D 6 H...
question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...
3 6 7 8 9 10 11 12 13 14 Here are the shopping times (in minutes) for a sample of 21 shoppers at a particular computer store: 26, 23, 44, 41, 38, 35, 31,28,25, 22, 43, 24, 24, 21, 21, 21, 43, 43, 39, 39, 39 Draw the histogram for these data using an initial class boundary of 20.5, an ending class boundary of 45.5, and 5 classes of įqual width. Note that you can add or remove classes...
can you explain how to fo the mean variance wnd z score and st dev each path Problem 17-11 The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 5-7-10 8-10-14 11-12-13 11 14-18-26 8-8-8 5-6-7 6-6-6 2 13-13-13 10.5-13-15.5 10 10-12-14 10-11-12 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 answers to 2 decimal places.) Path 1-2-3-8-11 1-2-4-6-11 1-2-4-7-11 1-2-5-9-10-11 Mean...
You have this solution in Java, I am interested in this same solution for Python.One interesting application of two-dimensional arrays is magic squares. A magic square is a square matrix in which the sum of every row, every column, and bothdiagonals is the same. Magic squares have been studied for many years, and there are some particularly famous magic squares. In this exercise you will write code todetermine whether a square is magic.You should find that the first, second, and...