Question

QUESTION 1: TURN THIS GNATT CHART INTO AN ACTIVITY TABLE. FOR EXAMPLE THE TABLE SHOULD BE FORMATED LIKE THIS BUT MATCH THE DATA OF THE GNATT CHART BELOW,  Activity No. Activity Time (weeks) Immediate Predecessors Collect requirements Analyze processes Analyze data Design processe (THIS IS THE EXAMPLE OF A ACTIVITY TABLE FORMAT NOT THE SAME DATA AS THE GNATT CHART)

ONCE AGAIN, QUESTION IS TO CONVERT THE DATA IN THE GNATT CHART INTO ITS' ACTIVITY TABLE (ACTIVITY NO., ACTIVITY, TIME (WEEKS), IMMEDIATE PREDECESSORS..)pt , WS u Time 0 1 2 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Why are you trying to match the format of a Gnatt chart for a Job shop scheduling with that for Project management?

The project management Gantt chart for the given problem will be as follows:

Activity-1 Activity-2 Activity-3 Activity-4 Activity-5 Activity-6 Activity-7 Activity-8 Activity-9 Activity-10 Weeks 1 2 3 4

Add a comment
Know the answer?
Add Answer to:
QUESTION 1: TURN THIS GNATT CHART INTO AN ACTIVITY TABLE. FOR EXAMPLE THE TABLE SHOULD BE...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1...

    Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1 3 Analyze data 4 2 4 Design processes 18 2 5 Design data 6 3 6 Design screens 6 3,4 7 Design reports 12 4,5 8 Program 10 6,7 9 Test and Document 14 7 10 Install 4 8,9 Construct a network diagram & calculate the earliest expected completion time/s

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

  • Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity...

    Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • Question 24 (20 points) Use the following table of related activities with their activity times (weeks). Q24-1) Type your answers by the order of ES, EL, LS, LF, Slack for each activity. For ex...

    Question 24 (20 points) Use the following table of related activities with their activity times (weeks). Q24-1) Type your answers by the order of ES, EL, LS, LF, Slack for each activity. For example, A. Х, Х, Х, Х, Х Q24-2) Determine the critical path. Immediate Activity Activity Predecessor Time ESEFLSLqslack (weeks 4 C A DIB E A FIB G C,D H |D,F 7 6 5 4 6 G, H, I J Question 24 (20 points) Use the following table...

  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • 1. Make a pert chart out the data Table #1: Patio Deck Re-Build Project Activity Time...

    1. Make a pert chart out the data Table #1: Patio Deck Re-Build Project Activity Time Activity Identity Milestones Activity's Immediate Predecessor (What activity must occur before this one...) (davs) ZA None A в 3c B D B JE B B E GG B 1н B 91 B 20 A 2K B B Bidding Phase Complete Estimate w/Plans Receive City Biddine Permits Receive Bid from Excavator 1 Receive Bid from Excavator 2 Receive Bid from Excavator 3 Receive Bid for...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • 0 25. Time (minutes) 10 35 Activity 2 1. Using any guidelines provided by your teacher, develop a testable question...

    0 25. Time (minutes) 10 35 Activity 2 1. Using any guidelines provided by your teacher, develop a testable question about yeast fermentation. 2. Design an experiment to test your question. Consider the following as you frame your experiment: Question -What are you testing in your experiment? What are you trying to find out? Hypothesis-What do you think will happen? Why do you think so? What do you already know that helps support your hypothesis? Materials -What materials, tools, or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT