Question

The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for the next year. The relevant cost data and forecast for the next 4 quarters is provided below. The company currently has 20 employees and works one 8 hour shift each day with 2 paid 15 minute breaks. Assume each quarter has 65 working days, and that it currently has no units in stock. Use this information and the information from the table to answer the questions below.

P301 Problem 7 The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for the next yeaQ3) Assume the company decides to use the number of workers identified in question 2 above. They also plan to use oveertime t

0 0
Add a comment Improve this question Transcribed image text
Answer #1

part I

1)

Qtr1 Qtr2 Qtr3 Qtr4
Forecast 1500 1200 2100 1650
Production 1500 1200 2100 1650
Hours req. 10500 8400 14700 11550
Workers Req. 2 -5 13 -6
Workers used 22 17 30 24

Working hours per quarter per employee = 65*7.5 hours = 487.5 so workers required = Hours required/487.5

Workers required = Additional workers that are needed to satisfy Workforce needed for the production

2)

Qtr1 Qtr2 Qtr3 Qtr4
Forecast 1500 1200 2100 1650
Production 1612.5 1612.5 1612.5 1612.5
Hours req. 11287.5 11287.5 11287.5 11287.5
Workers Req. 3 0 0 0
Workers used 23 23 23 23

Production = 6450/4 = 1612.5

Workers required = Additional workers that are needed to satisfy Workforce needed for the production

3)

Qtr1 Qtr2 Qtr3 Qtr4
Forecast 1500 1200 2100 1650
Workers used 23 23 23 23
Hire/(Fire) 3 0 0 0
Production 1612.5 1612.5 1612.5 1612.5
Production-Forecast 1612.5 1612.5 1612.5 1612.5
Inventory:
B.I 0 112.5 525 37.5
E.I 112.5 525 37.5 0
Average 56.25 318.75 281.25 18.75
Overtime production 0 0 0 0
Overtime hours 0 0 0 0
Hiring cost 6000 0 0 0
Firing cost 0 0 0 0
Regular Output 203175 203175 203175 203175
O.T 0 0 0 0
Subcontract 0 0 0 0
Inventory 1040.625 5896.875 5203.125 346.875
Backorder 0 0 0 0
Total cost 210215.6 209071.9 208378.1 203521.9
Total cost for plan 831187.5

Overtime cost for this plan = 0

Add a comment
Know the answer?
Add Answer to:
The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for...

    02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...

  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

  • Q1. Prestige, Inc. needs an aggregate plan for its product line. As part of trying to...

    Q1. Prestige, Inc. needs an aggregate plan for its product line. As part of trying to maintain a lean production system, management prefers a constant workforce, no overtime, and constant production level. Relevant data follows: Item Data | Units Data Item | Data | Units Production time required labor hours per unit 4.5 Units % of monthly forecast 0% Hiring cost $10,000 Item Ending inventory target Shortage cost per person Straight time labor cost per hour $75 per unit Laying...

  • You would like to construct an aggregate production plan for product X341 for the next four...

    You would like to construct an aggregate production plan for product X341 for the next four quarters. Cost of regular production 100 $/u Cost of overtime production 150 $u Inventory holding cost 15 S/u/qtr Cost of increasing production 120 $/u Cost of decreasing production 160 $/u Subcontracting cost 170 $/u Stockout cost 180 $/u Previous quarter's regular output 1500 u Beginning inventory level-30 u The forecasted demand for the next four quarters are: 1000, 300, 600, and 900 units. Suppose...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

  • A disk drive manufacturer is in need of an aggregate plan for July to December. The...

    A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...

  • You would like to construct an aggregate production plan for product X341 for the next four...

    You would like to construct an aggregate production plan for product X341 for the next four quarters. Cost of regular production = 60 $/u Cost of overtime production = 90 $/u Inventory holding cost = 10 $/u/qtr Cost of increasing production = 70 $/u Cost of decreasing production = 120 $/u Subcontracting cost = 115 $/u Stockout cost = 130 $/u Previous quarter's regular output = 225 u Beginning inventory level = 25 u The forecasted demand for the next...

  • A small manufacturer of specialty welding equipment has developed a level production plan for the next...

    A small manufacturer of specialty welding equipment has developed a level production plan for the next four quarters, as seen below: Supply/Demand Info Pre-Q1   Q1 Q2 Q3 Q4    Forecast (demand) 2,300 2,760 3,680 5,980 Regular production 3,680 3,680 3,680 3,680 Subcontract production Ending inventory Hired employees 11 Fired employees Total employees 21 32 32 32 32 The table below shows additional relevant information: Capacity Information & Cost Variables    Production rate (units/employee/quarter) 115 Subcontractor capacity (units/quarter) 480 Regular production...

  • PP.61 A small manufacturer of specialty welding equipment has developed a level production plan for the...

    PP.61 A small manufacturer of specialty welding equipment has developed a level production plan for the next four quarters, as seen below: Supply/Demand Info Pre-Q1   Q1 Q2 Q3 Q4 Forecast (demand) 4,600 4,600 3,680 6,440 Regular production 4,830 4,830 4,830 4,830 Subcontract production Ending inventory Hired employees 12 Fired employees Total employees 30 42 42 42 42 Additional Information: Capacity Information & Cost Variables    Production rate (units/employee/quarter) 115 Subcontractor capacity (units/quarter) 480 Regular production cost/unit $70 Holding cost/unit/quarter $14...

  • Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000;...

    Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000; winter, 18,800. At the beginning of spring, you have 66 workers and 990 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT