During the project meeting, you and your colleagues are reviewing the Risk Management section in the...

During the project meeting, you and your colleagues are reviewing the Risk Management section in the Project Plan (PP). You notice that it only lists10 risks in alphabetic order and none of them are related to security. You also notice from System Requirements Document (SRD) review meeting held last week that there is no security requirements listed in SRD. What should you do if you are not the project manager?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

SOLUTION:

From given data,

During the project meeting, you and your colleagues are reviewing the Risk Management section in the Project Plan (PP). You notice that it only lists10 risks in alphabetic order and none of them are related to security. You also notice from System Requirements Document (SRD) review meeting held last week that there is no security requirements listed in SRD. What should you do if you are not the project manager

In the project meeting, I and my colleagues are reviewing the risk management section in the project plan. After the potential risks have been identified,

the project team then evaluates the risk based on the probability that the risk event will occur and the potential loss associated with the event.

Not all risks are equal. Some risk events are more likely to happen than others, and the cost of a risk event can vary greatly.

Evaluating the risk for the probability of occurrence and the severity of the potential loss to the project is the next step in the risk management process.

I'll decide to make the review report on the Risk Management section. Having criteria to determine high impact risks can help us to narrow the focus on a few critical risks that require mitigation.

In which we'll define all the risk management in the project report and then send it to the project manager so that they must be ready to plan and schedule the reviewing the project plan.

After that we conduct Project meeting which helps to improve the project and resolve the project risk.

You make sure that the project is in progressing as planned and that any problem is being solved the right way.

Please thumbs-up / vote up this answer if it was helpful. In case of any problem, please comment below. I will surely help. Down-votes are permanent and not notified to us, so we can't help in that case.

Add a comment
Know the answer?
Add Answer to:
During the project meeting, you and your colleagues are reviewing the Risk Management section in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project 1 Design, develop and document a risk management plan related to: the reduction of accidents,...

    Project 1 Design, develop and document a risk management plan related to: the reduction of accidents, illness or incidents relating to worker or general public safety the prevention of operational discontinuity the need for new or innovative improvement/ changes in processes or procedures (and the associated risks) environmental impact issues—including resource use and management You might choose another risk area relevant to the organisation for which you work. If you do you will need to describe the organisation and the...

  • Project risk management is an iterative process that begins with a plan for how risks will be man...

    Project risk management is an iterative process that begins with a plan for how risks will be managed throughout the life of the project. Risks must first be identified and analyzed. Then risk responses and action steps must be developed. The risk management plan should also include the steps, processes, or procedures that will be used to continually monitor risk during the project. Defining requirements for a process improvement project can be particularly challenging. Depending on the extent and complexity...

  • During this class you will be learning how to manage project risks and opportunities. The risk...

    During this class you will be learning how to manage project risks and opportunities. The risk management process, which is part of the project management process, consists of these primary steps: Understand the environment. Understand the organization's approach to risk management and establish overall priorities. Identify the risks. Recognize potential project risks and build an understanding of them. Analyze the risks and potential impact. Assess the risks, determine the probability of their occurrence, and identify the potential impact. Create the...

  • Project 1 Design, develop and document a risk management plan related to: the reduction of accidents, illness or incidents relating to worker or general public safety the prevention of operati...

    Project 1 Design, develop and document a risk management plan related to: the reduction of accidents, illness or incidents relating to worker or general public safety the prevention of operational discontinuity the need for new or innovative improvement/ changes in processes or procedures (and the associated risks) environmental impact issues—including resource use and management You might choose another risk area relevant to the organisation for which you work. If you do you will need to describe the organisation and the...

  • Concept of Operations, Process Improvement and Risk Management Add a process improvement plan section to the...

    Concept of Operations, Process Improvement and Risk Management Add a process improvement plan section to the CONOPS. The plan needs to address how the operational staff will review data and a process for continuous improvement. Risks to the surgical unit’s operations need to be listed as well, along with how each risk will be mitigated.

  • Use the following scenario. Review the scenario first and then continue on with your assignment. Consider...

    Use the following scenario. Review the scenario first and then continue on with your assignment. Consider saving the PDF or printing it out for your reference. You have been meeting with the CEO, the project sponsor, your manager, and the heads of all the other departments to discuss the project and their expectations. You are starting to be concerned about the level of risk of this project and whether or not the organization really understands it. As far as you...

  • A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement...

    A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement Risk Responses Perform Qualitative Risk Analysis Plan Risk Responses A project has the following risks: 20 percent probability of a 14-day delay in the receipt of customer requirements; 10 percent probability of a 21 -day delay in the procurement process; 50 percent probability the integration will take 14 days longer than planned. What is the expected value of these events? 49 days Seven days...

  • A) We require you to describe how you would use project management tools to develop and implement...

    A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: project management software Gantt and bar charts critical path method (CPM) Program Evaluation Review Technique charts (PERT) cost schedule control system life cycle cost analysis logistics support analysis spreadsheets technical resources B) Whilst completing your project plan, ensure you include the following: deliverables   work breakdown budget and allocation of resources      timelines risk management...

  • You are the primary client on a large extranet development project. After carefully reviewing the requirements...

    You are the primary client on a large extranet development project. After carefully reviewing the requirements definition document, you are positive that there are missing, ambiguous, inaccurate, and unclear requirements. The project manager is pressuring you for your sign-off on because he has already received sign-off from five of your co-workers. If you fail to sign off on the requirements, you are going to put the entire project at risk because the time frame is nonnegotiable. What would you do?...

  • Project Management Using the Risk Analysis Form (see attached), list at least 4 risks to your...

    Project Management Using the Risk Analysis Form (see attached), list at least 4 risks to your project Number the Impact and Occurrence Calculate the total Risk Number, then List ways you could manage these risks The rating scale for Impact and Occurrence is 1-5 with 1 being low or almost none and 5 being high. Risk Analysis Form Risk Impact (1-5) Probability (1-5) Total Risk Management Actions

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT