A watch list is an output of which risk management process?
Perform Quantitative Risk Analysis |
||
Implement Risk Responses |
||
Perform Qualitative Risk Analysis |
||
Plan Risk Responses |
A project has the following risks: 20 percent probability of a 14-day delay in the receipt of customer requirements; 10 percent probability of a 21 -day delay in the procurement process; 50 percent probability the integration will take 14 days longer than planned. What is the expected value of these events?
49 days |
||
Seven days |
||
11.9 days |
||
35.8 days |
During project planning, a project manager is planning the upcoming project team meetings that will occur during project executing. What should she include in these meetings that will have the biggest impact on the project?
Review of upcoming identified risks |
||
Assignment of activities to team members |
||
Review of the action item list |
||
Estimating costs |
Q1. The answer is c) Perform Qualitative Risk Analysis process. It is made up of tasks that are determined to be of too low priority or low impact to move further in the risk management process. Thus, the correct answer is (c).
Q2. Given, the delays in various tasks with their risk probabilities.
Task Delay Risk Probability
Receipt of customer requirements 14 days 20%
Procurement process 21 days 10%
Integration 14 days 50%
Expected value of these events= 0.2*14+0.1*21+0.5*14= 11.9 days Ans
Q3. The project execution phase generally starts out with a project kick-off meeting. In this meeting, various stakeholders are invited to discuss the project plan and share their views on any upcoming foreseeable concerns. So, a) review of upcoming identified risks is the most important agenda for the execution phase meetings since any risk which team members fail to identify can adversely impact the project in terms of increased cost or delayed schedule or altogether change in deliverables. Hence, it is very important to identify risks in execution phase and act in a proper manner for its minimization.
A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement...
QUESTION 50 The risk urgency is a tool and technique used for O Plan Risk Responses O Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis QUESTION 50 The risk urgency is a tool and technique used for O Plan Risk Responses O Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis
QUESTION 42 The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the following EXCEPT O Relative probability or likelihood of occurrence of identified risks O Impact on project objectives if the identified risks occur OA mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy O The organization's risk tolerance associated with the project constraints of cost, schedule, scope, and quality QUESTION 42 The Perform Qualitative Risk...
Project risk management is an iterative process that begins with a plan for how risks will be managed throughout the life of the project. Risks must first be identified and analyzed. Then risk responses and action steps must be developed. The risk management plan should also include the steps, processes, or procedures that will be used to continually monitor risk during the project. Defining requirements for a process improvement project can be particularly challenging. Depending on the extent and complexity...
Perform numerical analysis of identified individual project risks to quantify overall project risk exposure. Quantitative analysis/simulation used to support risk response planning, one for the highest positive and one for identified highest negative risk.
B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all af the following EXCEPT A. B. C. Relative probability or likelihoad of occurrence of identified risks. Impact an praject abjectives if the identified risks accur A mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy. The organization's risk tolerance assaciated with the praject constraints of cast,...
Risk assessment refers to the overall process of risk identification, risk analysis and risk evaluation; in the scope of the Risk Management Planning Process. Risk identification generates a list of the risks that may have an impact on the project and create uncertainty about whether or not it will achieve or exceed its objectives. Risk analysis is the systematic use of available information to develop an understanding of the risk. Risk evaluation is the process of comparing the estimated level...
Project Management Using the Risk Analysis Form (see attached), list at least 4 risks to your project Number the Impact and Occurrence Calculate the total Risk Number, then List ways you could manage these risks The rating scale for Impact and Occurrence is 1-5 with 1 being low or almost none and 5 being high. Risk Analysis Form Risk Impact (1-5) Probability (1-5) Total Risk Management Actions
Qualitative risks are typically categorized by a group of experts to determine the probability and the impact to project objectives. In the example below, consider the next steps that should be taken as project manager to assemble a group of experts to participate. Who would you select and why? Project Management Body of Knowledge (PMBOK) defines risks as “an uncertain event or condition, that if it occurs, has a positive or negative effect on one or more project objectives” (ProjectRiskCoach,...
•Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...
Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...