Question

A senior MIS design class project team has developed the following schedule of activities for their...

A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Please construct a project network to answer the following questions.

Activity

Time (days)

Immediate Predecessor

A

Find client

4

---

B

Write prospectus

2

A

C

Obtain approval from client and professor

3

B

D

Complete programming

12

C

E

Do industry background research

10

---

F

Write final paper

7

D, E

G

Write oral report

5

D, E

How many days of slack does Activity G have?

A. 10 days

B. 0 days

C. 11 days

D. 2 days.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: D. 2 days

Explanation:

step 1 find early start, and early finish from th start of the project for each activity
Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D
A 4 0 4
B 2 4 6
C 3 6 9
D 12 9 21
E 10 0 10
F 7 21 28
G 5 21 26
step 2 Find Maximum EF and keep it as the LF of last activities

28 is the Max EF.

step 3 calculate LS for each activity after calculating its EF's.
Activity Duration, D Early start, ES=Max of early finish of preceeding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF
A 4 0 4 4 0 0
B 2 4 6 6 4 0
C 3 6 9 9 6 0
D 12 9 21 21 9 0
E 10 0 10 21 11 11
F 7 21 28 28 21 0
G 5 21 26 28 23 2

Hence activity G has slack of 2 days.

Add a comment
Know the answer?
Add Answer to:
A senior MIS design class project team has developed the following schedule of activities for their...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The table below shows a number of tasks required for the successful completion of a project....

    The table below shows a number of tasks required for the successful completion of a project. Activity Days Immediate Predecessor(s) A 4 B 2 A C 5 A D 7 A E 2 B F 5 B,C G 6 D,E,F Draw the network diagram for this project highlighting Early Start, Early Finish, Late Start and Late Finish and slack. Please show your answer by using the format shown below.                                                                                                                                  Table template: Activity A B C D E F G Early...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • The following activities of a hospital expansion project has been identified in the following table. First,...

    The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • A small software development project has eight major activities. The times are estimated and prov...

    A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT