Six projects have been identified for possible implementation by a company that makes dry ice blasters,...

Six projects have been identified for possible implementation by a company that makes dry ice blasters, machines that propel tiny dry ice pellets at supersonic speeds so they flash freeze and then lift grime, paint, rust, mold, asphalt, and other contaminants off in-place machines and a wide range of surfaces. The present worth of each project has been determined. Identify all acceptable mutually exclusive bundles if the budget limitation is $23,000. Arrange the acceptable bundles in such a way that the total PW values are in ascending order.

Project Project PW at 15%, $
L 29,000
M 11,000
N 41,000
O 35,000
P 6,000
Q 2,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

projects are organized in ascending order on the basis of PW as follows:

Project Project PW at 15%, $
Q 2,000
P 6,000
M 11,000
L 29,000
O 35,000
N 41,000

On the basis of PW only three projects Q, P and M are having PW less than of $23000.

So, feasible bundles are :

QPM = 2000 + 6000 + 11000 = $19000

QP = 2000+6000 = $8000

PM = 6000+11000 = $17000

So, Q, P & M projects will be selected.

Add a comment
Know the answer?
Add Answer to:
Six projects have been identified for possible implementation by a company that makes dry ice blasters,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Six projects have been identified for possible implementation by a company that makes dry ice blasters,...

    Six projects have been identified for possible implementation by a company that makes dry ice blasters, machines that propel tiny dry ice pellets at supersonic speeds so they flash freeze and then lift grime, paint, rust, mold, asphalt, and other contaminants off in-place machines and a wide range of surfaces. The present worth of each project has been determined. Identify all acceptable mutually exclusive bundles if the budget limitation is $23,000. Arrange the acceptable bundles in such a way that...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT