Question

Resource Loading and Leveling Concept 1) The typical resource managed in most projects is people’s time....

Resource Loading and Leveling

Concept 1) The typical resource managed in most projects is people’s time. Additional resources that may need to be considered are:

  • Machine time/capacity – Does the project require time on a specific machine, particularly one that is a scarce resource?
  • Facility availability – Are facilities physically large enough to serve the needs of the project? In labor-intensive projects this could be the facility of office space including desks, chairs, phones, and computers.
  • Transportation – Some projects, such as a major demolition or a large convention, may put unusual strains on the transportation capacity of an area.

Concept 2 )   Resource loading is the level of demand placed upon individual resources during a specific time interval in a project schedule.

Concept 3)  Resource leveling seeks to minimize fluctuations in the resource demand created by a project.


Concept 4) The activity slope, associated with “crashing” a project, identifies the trade-off between time and money when duration is reduced to expedite a project. Generally, the cost to perform an activity goes up as its duration is reduced.

Why is it important for a project manager to resource load their project schedule? What problems may arise if a project manager does not resource load their project schedule?



Your comments should be supported by research that you reference at the bottom of your post

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Resource loading generally states the amount of individual resource that is required by existing schedule in a particular time.

It is important for a project manager to resource load their project schedule for following reasons:

  • It ensures that someone is directly responsible for assigned responsibility on the project schedule.
  • It also holds importance in workload management for determining how many activities a team member can individually work on.
  • Resource load information loaded into project schedule allows project manager to perform several types of analysis.
  • It enables manager to load specific types of equipment and labor by discipline.
  • It helps project manager to identify and eliminate many unwanted factors during the planning stages.
  • By executing it properly project manager can reduce the overall project schedule without increasing resources

Problems that may arise if a project manager does not resource load their project schedule are as follows:

  • Unexpected issues may arise if resource load is not done.
  • Over allocation can occur if project managers fail to resource load their project.
  • Under allocation of resource can occur.

Reference:

  • William Bow, PMP & Bruce Taylor; 2008; Project Management Communications; Wiley Publishing Inc.; Indiana.
  • Kathy Schwalbe; 2007; Introduction to Project Management, Second Edition; Course Technology Cengage Learning, Boston, USA.
Add a comment
Know the answer?
Add Answer to:
Resource Loading and Leveling Concept 1) The typical resource managed in most projects is people’s time....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT