Question

I have this assignment that I need help with, I turned it in but I got...

I have this assignment that I need help with, I turned it in but I got a bad grade for it, could someone please help me take an overview of it or take a look at it.
but I want to change the project to Fundraising for kids in need all over the world. Because there is an assignment that I did in the past that is connected to it.

Develop a work breakdown structure (WBS) for the project. Break down the work to level 3 or level 4, as appropriate. Be sure to base your WBS on the project scope statement, stakeholder requirements, and other relevant information. Remember to include the work involved in selecting the rest of your project team and outside resources as well as coordinating with the cloud-computing providers. Use the project management process groups as level 2 WBS items or include project management as a level 2 WBS item to make sure you include work related to managing the project.

Work Breakdown Structure Template for Project Name

Prepared by:   Date:

  • The project scope statement is to check the internet for stuff that shouldn’t be there or a bad influence for the new internet users
  • Stakeholder requirements
    • Create process and application, using the date
    • Create links between the process and application models
    • Create process and application views, using the models
    • Create a link between the views
    • Create a visualization, using the views
    • Publish a visualization to be a view to have for stakeholders
  • There is relevant information to know when you are doing a work break down structure.
    • The key project deliverable that organizes the team work into manageable sections
    • The knowledge of the work breakdown structures deliverable project that must be executed by the project team
  • Selecting a team for your project
    • Find members that are well-Organized and self-disciplined.
    • Find members that are seeking to be in manger point of view in project
    • Find the best fit for the role to get you the outcome of the project goal.
    • Find members from a different cloud to help overview the project goals and requirements, that will get you the best result for your project.

Project about an overall check of the internet

You have to evaluate the current software program

  1. You must identify the problems used in the program

1.1 make sure that the project bugs are based on real answers or facts.

1.2 check what to fix

1.2.1 check if there are any problems that you need to fix to make the internet better.

1.2.2 check what to fix and what are the requirements to do it.

1.3 estimate and review the problems that you are going to fix in a project view as a company.

1.4 estimate the time

  1. Project scheduling

2.1 Project charter

2.2 Project plan

2.2.1 Make a time schedule

2.2.2 Keep a timing plan

2.3 Technical check

2.4 Steering check

  1. The design
    1. De-bug the process of the project
    2. And de-bug the database

3.2.1 Data import

3.2.2 Data export          

  1. Debugging
  2. Checking the design for any problems
  1. Training and testing
    1. A whole unit testing
    2. User acceptance for testing such as UAT
      1. UAT for Applications
      2. UAT for servers
    3. Training all the clients
    4. And last check the whole project and system testing
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Following is creating a work breakdown structure (WBS) - a visual display of all the event deliverables after broken down into workable chunks. To get those extensive number of tasks under the control, the event manager can group them into separate manageable units required skills and knowledge accordingly. The compelling reasons to use a WBS in a project are that it will “help the project team to have precise communication about what is expected at each stage of the project, to allocate resources and personnel appropriately”; “facilitate communication about the specifics of the project with stakeholders, like management, board, or end-users, to make sure nothing is overlapping or missing” and “help to accurately and specifically define and organize the scope of the total project”.

The WBS is fundamental for the next techniques which are resources and tasks and responsibilities analyzing. Resources analysis helps the event management to decide on what services, goods or positions (human resources) are sourced from client or sponsor, outsourced to the supplier or specially created for the event. The output of identifying tasks and responsibilities technique is the task responsibility chart or document from which all stakeholders can have information on a list of tasks, who is in charge, when is the deadline and how the completion of tasks will be communicated.

Overall, the five phases - initiation, planning, implementation, the event, and shutdown, consist the life circle of a project and describe the event management process from a project management perspective. Different management techniques and tools will be required in each of the phases. The techniques form a process of tasks that overlap. Several areas of knowledge of administration, marketing, design, operation, and risk management will be used over the whole process and to create control plans and documents such as task responsibility chart, checklist, schedules, resource analysis, contract management, financial plan, budget, risk management, and stakeholder management plan

Add a comment
Know the answer?
Add Answer to:
I have this assignment that I need help with, I turned it in but I got...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Application Work Breakdown Structure In a single-person endeavor, it is relatively easy to understand the duties...

    Application Work Breakdown Structure In a single-person endeavor, it is relatively easy to understand the duties and responsibilities of the person. However, when you work in groups, the work should be distributed as appropriately as possible among the team members. As a PM, you can create a diagram called the work breakdown structure (WBS), which specifies the activities that need to be carried out and the responsibilities of the individuals. Complete the following tasks: 1. Write a set of tasks...

  • 1) "Once you have identified all of the stakeholders, it is important to determine which group...

    1) "Once you have identified all of the stakeholders, it is important to determine which group of stakeholders holds the most power and which group may have the greatest impact in the overall outcome of the project. " a) true b) false 2) You are leading an international team and you are considering how this might impact your communications and decision making processes as a team. Your goal is to _______________. a) adapt the work processes to cope with the...

  • Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views...

    Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views on the following: What is scope planning and scope creeping? What are some of the ways to avoid problems and manage scope correctly? You've been assigned the project of setting up a LAN with a broadband connection in your office. You need to provide internet connectivity for web browsing to all users. All the computers have Microsoft Windows 7 software installed. Based on your...

  • Create a work breakdown structure

    Create a work breakdown for the project, the WBS should include up to the third level and must demonstrate dividing work up to multiple work items. A graphic chart must be used. Information :You have decided to enter a South African innovative App competition. The competition requires you (and your team) to think of an innovative idea that could lead to the development of an App aimed at assisting and benefiting south African citizens in the following category: (Government services)Some fundamental...

  • I need help with an ITEC project

    Team Project MILESTONE 1 1. Choose a Team Facilitator: This person will lead the project and work with members on assigning tasks. 2. Choose someone who everyone sends their completed work to who will compile it and create the PowerPoint Presentation. 3. Exchange contact information with team members. 4. FINALLY!! EVERYONE MUST PARTICIPATE TO GET YOUR GRADE!!! Examine the DFD’s on page 497 of your text. Note how the context diagram has been exploded to show more detail. Note that...

  • In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software applicatio...

    In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software application that you have selected. Prepare the WBS, and submit the file to your instructor. This assignment is due Sunday at 11:59 p.m. All assignments should be uploaded in the Assignment area. Project Software Options There are many project management software applications that are designed to help develop project plans and schedules as well as keeping track of these plans and creating...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • Determine the following: -organizationap chart -stakeholder register -charter -scope statement -WBS -Schedule assignment -cost assignment -earned...

    Determine the following: -organizationap chart -stakeholder register -charter -scope statement -WBS -Schedule assignment -cost assignment -earned value assignment Problem Case Summary Wilmont's is a top-ranked US retail pharmacy with more than 8,000 stores nationwide. The company is secretly considering delivering prescriptions by flying drone. Drone Tech, a small firm in San Francisco, CA announced the approach in March, and Wilmont's has made an agreement with DroneTech to prototype this project in the San Francisco area. Drone Tech will provide the...

  • I need help with this assignment I am in project management You’ll be making a communication...

    I need help with this assignment I am in project management You’ll be making a communication plan for the project. Use Table 10.1 as a guide. For each row, explain why you chose the values you did. This is an essay. Everything is below. Project Communications Management: Case Study Several issues have arisen on the Global Treps Project. Ashok, your team member in India, broke his wrist playing tennis yesterday and cannot work on the project at all for three...

  • (Use the case of “Global Treps”) You have been selected as the project manager for the Global Tre...

    (Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT