Question

The project described in the table uses the same resource for activities A, B, C, and...

The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?

Activity Duration Predecessor WBS ID
W 4 -- 12
A 3 W 16
B 4 W 15
C 5 W 13
D 6 W 14
E 1 B 17
Z 7 A, E, C, D 18

Activity A

Activity B

Activity C

Activity D

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans Activity A

Activity A duration is shortest among A, B, C and D. Also, all four activities have same predecessor W and are ready to start at the same time.

Add a comment
Know the answer?
Add Answer to:
The project described in the table uses the same resource for activities A, B, C, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • 5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predec...

    5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...

  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • 3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

    3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time. Table 1: Activities, predecessors and duration time. Activity Predecessor Duration A - 2 B B 2 C A,B 1 D C,D 2 E D 3 Table 2: Activities and their required...

  • 3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

    3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time. Table 1: Activities, predecessors and duration time. Predecessor Duration 2 Activity A B с D 2 1 B AB C.D D 2 E 3 Table 2: Activities and their required number...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • 5. (4 points) The Figure shows the project network with normal durations of the activities (in...

    5. (4 points) The Figure shows the project network with normal durations of the activities (in weeks). The following table shows the normal durations, shortest possible durations, achieved at extra cost, & the acceleration cost per time unit. Activity Immediate predecessor(s) Normal duration Shortest possible duration Unit cost of acceleration ($ in Thousands) 40 C 5 4 50 80 DA 5 1 50 (6,5, 40) (5, 4, 50) Start End D (5, 1, 50) (4, 3, 80) Develop all possible...

  • The following table provides a list of activities in a project, along with their respective durations...

    The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • B. Resource Loading (33 pts). The network diagram below represents a project plan. a. b. C....

    B. Resource Loading (33 pts). The network diagram below represents a project plan. a. b. C. Compute the early, late, and slack times. Include your diagram in your paper What is the project duration? What is the critical path -illustrate it on your diagram (such as a dotted line). Ch 8 Assignment Resources: P(ainter); T(rimmer) 0 A START P & T ES ID EF SL Resour LS Dur LF 2 As your text stated, a plan isn't a schedule until...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT