TWA is scheduling the repair of five identical 707 aircraft next month. The time to repair each of the aircraft is given below: Aircraft: 1 2 3 4 5 Repair Time (Days): 6 7 2 5 8 If the sequence of repair were 1-2-3-4-5, what would the mean job flow time be for the aircraft?

a. 14 b. 16.4 c. 28 d. 82

0 0
Add a comment Improve this question Transcribed image text
Answer #1

To calculate the mean job flow time we have to first calculate the flow time for each job which is the cumulative sum of the processing time .

If the sequence of repair is 1-2-3-4-5, the flow time for each job are calculated as follows

Job processing time flow time

1 6 6

2 7 13 (As 6+7)

3 2 15 (As 13+2)

4 5 20 (As 15+5)

5 8 28 (As 20+8)

Mean flow time = Sum of the flow time for each job/Number of jobs

= (6+13+15+20+28) / 5

= 82/5

= 16.4

So the answer is option b

Add a comment
Know the answer?
Add Answer to:
TWA is scheduling the repair of five identical 707 aircraft next month. The time to repair...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 12. The company is scheduling the repair of buses for next month. Currently, there are five...

    12. The company is scheduling the repair of buses for next month. Currently, there are five buses needing repair (all are similar). Bus: Repair Time in Days: 5 8 3 6 7 The minimum mean flow time of the buses in the repair shop is which of the following? a. 5.8 days c. 29 days V W X Y Z b. 15 days d. 75 days

  • Problem 1: A forensic audit firm has five audit jobs remaining at a point in time....

    Problem 1: A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4 and 5. The respective audit times (in days) and the remaining days before the due date are given in the table below. | Audit job Time required 10 28 30 Due (at the end of day 60 45 30 32 31 le a) Determine the job sequence using each of these priority rules: (1)...

  • : A forensic audit firm has five audit jobs remaining at a point in time. The...

    : A forensic audit firm has five audit jobs remaining at a point in time. The audits are labeled as jobs 1, 2, 3, 4 and 5. The respective audit times (in days) and the remaining days before the due date are given in the table below. Audit job Time required Due (at the end of) day 1 11 61 2 29 45 3 31 31 4 1 33 5 2 32 Determine the job sequence using each of these...

  • Operations Scheduling. You are a manager of an injection molding shop, and need to schedule several...

    Operations Scheduling. You are a manager of an injection molding shop, and need to schedule several jobs on your largest molding machine. You decide to restrict the order of your choices somewhat to take an advantage of subsequent processing that some jobs must undergo. There are six jobs to be scheduled on the molding machine. Job 1 should be done before job 4 and job 3 before job 5. Processing times, due dates (both in days) and the cost (as...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 18 B 3 14 C 4 9 D 5 19 E 2 11 Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____. a. more than 10 but less than or equal to 12 days....

  • 3. [Challenging Question - Scheduling for Rescuing Scuba Divers (20 pts)] Tom Cruise has worked as...

    3. [Challenging Question - Scheduling for Rescuing Scuba Divers (20 pts)] Tom Cruise has worked as an operations manager of Underwater Treasure Discovery Company in Miami, FL and recently he was assigned to make a schedule to dispatch deep-water robots to save five scuba divers needing urgent rescue out of danger under the deep sea. He must do a very brief assessment of how urgent each diver appears and need to determine the best sequence to save all five scuba...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____. a. more than 14 but less than...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • Five batch jobs (A,D,I,J,K) arrive at a computer at the same time(at time=0). The quantum size...

    Five batch jobs (A,D,I,J,K) arrive at a computer at the same time(at time=0). The quantum size of this system is 2 units of time. For each of the scheduling methods given below, calculate the average waiting time for the 5 jobs. Show (use timing diagrams) and explain your steps. You can prepare it by hand or on a computer. The following jobs and the estimated running times are defined: A 2 B 6 C 4 D 8 E 2 F...

  • Give the following scheduling algorithms : STRF, SJF, RR(q=6) Process Arrival Time Burst Time Priority P0...

    Give the following scheduling algorithms : STRF, SJF, RR(q=6) Process Arrival Time Burst Time Priority P0 2 15 3 P1 4 20 2 P2 0 28 1 P3 8 14 3

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT