Question

The key to being able to control the cost and schedule is having a plan to...

The key to being able to control the cost and schedule is having a plan to balance the following components of the triple constraint:

a. Period,capacity,budget

b. Time,resources,funding

c. Budget,scope,time

d. Depreciation,float,time

0 0
Add a comment Improve this question Transcribed image text
Answer #1

C. Budget, scope, time

The triple constraint model actually constitute time or schedule, resource or money and scope or quality

Add a comment
Know the answer?
Add Answer to:
The key to being able to control the cost and schedule is having a plan to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An economy of scope is best illustrated by being able to eliminate or reduce costs by...

    An economy of scope is best illustrated by being able to eliminate or reduce costs by A. Combing related value-chain activities of diffrent businesses into a single operation b. performing all of the value chain activities of related sister businesses a the same location c. extending the firms scope of operations over a wider geographic area d. expanding the size of a company's manufacturing plants e. having more value chain activities performed in house rather than outsourcing them

  • Outline of your project management plan (New iPhone with expandable storage) Prompt: Use this template to...

    Outline of your project management plan (New iPhone with expandable storage) Prompt: Use this template to complete your outline for this module. Add or delete letters as needed to complete each question. An outline does not always use complete sentences and does not need to be detailed. I. State your intentions for managing and balancing the scope-time-cost triangle. A. B. C. II. Highlight the key risks and obstacles that management will have to mitigate for the plan. A. B. C....

  • John is setting up his catering schedule and must determine which events he will be able...

    John is setting up his catering schedule and must determine which events he will be able to cater. Let ei = 1 if event i is selected, 0 if not, for i = 1,...,5. Write the appropriate constraint(s) for each condition. Conditions are independent. a. Choose no fewer than four projects. b. If project 1 is chosen, project 3 must be chosen. c. If project 4 is chosen, project 2 must not be chosen. d. Projects cost 40, 30, 60,...

  • Personal An accounting device used to plan and control resources of operational departments and divisions.Budget At...

    Personal An accounting device used to plan and control resources of operational departments and divisions.Budget At the beginning of the school year, Priscilla Wescott decided to prepare a A budget of estimated cash receipts and payments.cash budget for the months of September, October, November, and December. The budget must plan for enough cash on December 31 to pay the spring semester tuition, which is the same as the fall tuition. The following information relates to the budget: Cash balance, September...

  • Personal An accounting device used to plan and control resources of operational departments and divisions.Budget At...

    Personal An accounting device used to plan and control resources of operational departments and divisions.Budget At the beginning of the school year, Priscilla Wescott decided to prepare a A budget of estimated cash receipts and payments.cash budget for the months of September, October, November, and December. The budget must plan for enough cash on December 31 to pay the spring semester tuition, which is the same as the fall tuition. The following information relates to the budget: Cash balance, September...

  • Which of the following is NOT an element of the project master plan (i.e., project charter)?...

    Which of the following is NOT an element of the project master plan (i.e., project charter)? A. schedules B. PMBOK C. resource requirements D. personnel E. potential risks What should the results of the project launch meeting include? A. finalizing the project team B. finalizing the project’s schedule C. finalizing the project’s budget D. the project’s scope is understood E. selecting the project sponsor Which of the following is NOT a characteristic of effective project team members? A. They are...

  • 26.According to the DISC acronym, _____ relates to control, power, and assertiveness. independence steadiness influence dominance...

    26.According to the DISC acronym, _____ relates to control, power, and assertiveness. independence steadiness influence dominance competence 28.Which of the following is an example of asynchronous communications? Texting Mail and package delivery Instant messaging Computer-assisted conference Audio conference 33.Which of the following is an example of synchronous communications? Web log Fax Computer-assisted conference Mail and package delivery Electronic mail 36.A table reflecting Communication Escalation will contain information about all of the following EXCEPT: Priority Definitions Decision Authority Timeframe for Notification...

  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...

  • 9-1 A budget a. b. c. is a long-term plan. covers at least 2 years. is only a control tool. d. is...

    9-1 A budget a. b. c. is a long-term plan. covers at least 2 years. is only a control tool. d. is a short-term financial plan. e. is necessary only for large firms 9-2 Which of the following is part of the control process? Monitoring of actual activity Comparison of actual with planned activity Taking corrective action All of these. d. a. b. c. Investigating 9-3 Which of the following is not an advantage of budgeting? It provides a standard...

  • CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM...

    CME403/603 Scheduling and Project Control (10 pts PDM) For the following PDM schedule, manually perform CPM calculation to show items as on legend (key) node - ES, EF, LS, LF, TF, SF and FNF. Highlight critical path(s). 2. 25 8 8 D 11 | 42 46 34 42 3 8 1 3 B 10 C T 16 10 18 29 40 37 Start Finis h 2 0 0 9 12 37 G 24 10 12 4 Legend ES Activity N...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT