  1. What is the supportability analysis technique that is a the identification of the steps, spares and materials, tools, support equipment, personnel skill levels as well as any facility issues that must be considered for a given repair task. Also included in this analysis technique are elapsed times required for the performance of each task. This analysis technique covers both corrective and preventative maintenance tasks and, when complete, identify all physical resources required to support a system.


    FTA

    MTA

    FMEA

    RCM

    None of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans: MTA

Maintenance Task Analysis (MTA) is the identification of the steps, spares and materials, tools, support equipment, personnel skill levels and facility issues that must be considered for a given repair task. It also includes the elapse times required for the performance of each maintenance task. MTAs cover both corrective and preventative maintenance tasks and, when complete, identify all physical resources required to support a system.

Add a comment
Know the answer?
Add Answer to:
Question 14 What is the supportability analysis technique that is a the identification of the steps,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Maintenance Management, Please help with my assignment. Your task for this portfolio-type assignment is to write...

    Maintenance Management, Please help with my assignment. Your task for this portfolio-type assignment is to write a technical report that demonstrates how you would co-ordinate and execute the entire project. Your report should highlight the following topics covered in the module: 1. Project Management: Use the WBS to plan for your project, indicating all equipment involved, maintenance activities, human resource and all costs (10) (20) 2. Networks for Projects: Prepare a network diagram for all activities in your project; 3....

  • Maintenance Management, Please help with my assignment. Your task for this portfolio-type assignment is to write...

    Maintenance Management, Please help with my assignment. Your task for this portfolio-type assignment is to write a technical report that demonstrates how you would co-ordinate and execute the entire project. Your report should highlight the following topics covered in the module: 1. Project Management: Use the WBS to plan for your project, indicating all equipment involved, maintenance activities, human resource and all costs (10) (20) 2. Networks for Projects: Prepare a network diagram for all activities in your project; 3....

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • Answer the question: "what is a system?" It can be as short as one page or...

    Answer the question: "what is a system?" It can be as short as one page or as long as 3 pages. What is a System? The term “system” originates from the Greek term syst¯ema, which means to “place together.” Multiple business and engineering domains have definitions of a system. This text defines a system as: System An integrated set of interoperable elements, each with explicitly specified and bounded capabilities, working synergistically to perform value-added processing to enable a User to...

  • List one area of improvement that the group can make on analysis and synthesis. Make sure...

    List one area of improvement that the group can make on analysis and synthesis. Make sure all major applicable issues are identified. Have clear connections between ideas. List one area of improvement that the group can make on logic, clarity, and justification. Comment on whether or not the group has organized and developed ideas well with high degree of logical support and structure. List one area of improvement that the group can make on persuasiveness and overall effectiveness. Comment on...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • Read and Complete Case Study #2 –Managing People. The central components of your analysis should include issue identific...

    Read and Complete Case Study #2 –Managing People. The central components of your analysis should include issue identification, issue analysis, solutions, and potential limitations to your solutions. The case analyses serve to: a) Provide an opportunity to apply the class concepts in the solution of practical problems. b) Provide you with a common task through which you can learn to be more effective thinkers and problem-solves in your organizations. The written case analysis will be evaluated based on your effectiveness...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • Below is the information: It is important to understand the different leadership styles employed by nursing...

    Below is the information: It is important to understand the different leadership styles employed by nursing leaders in healthcare organizations and to understand their significance on nursing practice and patient outcomes, for better or for worse. Objective: Read the articles from Nursing Standard (PDF) and Bradley University (PDF). In -250 words, formulate an opinion on the following: 1. Reflect on an occasion where you experienced ineffective leadership (doesn't have to be in the hospital). What behaviors did they display? What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT