Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput...

Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.5 day, and its average queue time is 3.0 days.

Required:

Round your answer to 1 decimal place.

What is the Wait Time?

days

Process Time?

days

Inspection Time?

days

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Wait time = Delivery cycle time - Throughput time = 24 days - 14.0 days = 10.0 days

Process time = MCE × Throughput time = 0.20 × 14.0 days = 2.8 days

Inspection time = Throughput time - Process time - Move time - Queue time = 14.0 days - 2.8 days - 0.5 day - 3.0 days = 7.7 days

Add a comment
Know the answer?
Add Answer to:
Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT