1) Delivery cycle time = Wait time + Throughput time
29 days = Wait time + 13 days
Wait time = 29 days − 13 days = 16 days
2) MCE = Process time ÷ Throughput time
0.20 = Process time ÷ 13 days
Process time = 0.20 × 13 days = 2.6 days
3) Throughput time = Process time + Inspection time + Move time + Queue time
13 days = 2.6 days + Inspection time + 0.6 days + 3.0 days
Inspection time = 13 days − 2.6 days − 0.6 days − 3.0 days = 6.8 days
Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average mo...
Schurz Corporation's management reports that its average delivery cycle time is 24 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.5 day, and its average queue time is 3.0 days. Required: Round your answer to 1 decimal place. What is the Wait Time? days Process Time? days Inspection Time? days
Schurz Corporation's management reports that its average delivery cycle time is 28 days, its average throughput time is 16.0 days, its manufacturing cycle efficiency (MCE) is 0.30, its average move time is 0.6 day, and its average queue time is 3.0 days. a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations and final...
Schurz Corporation's management reports that its average delivery cycle time is 22 days, its average throughput time is 11.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.4 day, and its average queue time is 4.0 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations and...
2. Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.50, its average move time is 0.6 day, and its average queue time is 2.2 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations...
Rintharamy Corporation's management reports that its average delivery cycle time is 30 days, its average throughput time is 12.5 days, its manufacturing cycle efficiency (MCE) is 0.36, its average move time is 0.5 day, and its average queue time is 7.00 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) Wait time days b. What is the process time? (Round your answer to 1 decimal place.) Process time days c. What is the inspection...
Calculate Delivery Cycle Time, Throughput Time, and Manufacturing Cycle Efficiency! Inspection time .5 days Process time 2.8 days Wait time 16.0 days Queue time 4.0 days Move time .7 days
4. During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time was 0.8 day, process time was 2.8 days, wait time was 11.8 days, and move time was 0.6 day. Required: (15%) a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time.
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...
DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 3 4 Throughput time (days) Delivery cycle...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...