Question

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month

1

2

3

4

  Throughput time (days)

?

?

?

?

  Delivery cycle time (days)

?

?

?

?

  Manufacturing cycle efficiency (MCE)

?

?

?

?

  Percentage of on-time deliveries

73%

74%

79%

86%

  Total sales (units)

10,470   

10,540   

10,440

10,500

      Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)

1

2

3

4

  Move time per unit

0.6

0.6

0.5

0.6

  Process time per unit

0.5

0.7

0.6

0.7

  Wait time per order before start
   of production

9.5

8.0

5.0

4.0

  Queue time per unit

3.5

3.5

2.2

1.8

  Inspection time per unit

0.6

0.3

0.5

0.3

Required:

1-a.

Compute the throughput time for each month. (Round your answers to 1 decimal place.)

1-b.

Compute the manufacturing cycle efficiency (MCE) for each month. (Round your answers to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

1-c.

Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

3-a.

Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

Month 5

Throughput time

days

Manufacturing cycle efficiency (MCE)

%

3-b.

Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

Month 6

Throughput time

days

Manufacturing cycle efficiency (MCE)

%

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1) a)
Month 1 2 3 4
Throughput time in days:
Process time 0.5 0.7 0.6 0.7
Inspection time 0.6 0.3 0.5 0.3
Move time 0.6 0.6 0.5 0.6
Queue time during production 3.5 3.5 2.2 1.8
Total throughput time 5.2 5.1 3.8 3.4
b)
Manufacturing cycle efficiency (MCE): Process time ÷ Throughput time
Process time 0.5 0.7 0.6 0.7
Total throughput time 5.2 5.1 3.8 3.4 days
MAnufacturing cycle efficiency (MCE): Process time ÷ Throughput time 9.6% 13.7% 15.8% 20.6%
c)
Delivery cycle time in days:
Wait time to start of production 9.5 8 5 4
Throughput time 5.2 5.1 3.8 3.4 days
Total delivery cycle time 14.7 13.1 8.8 7.4
3)
a.
Month 5th
5
Throughput time in days:
Process time 0.7
Inspection time 0.3
Move time 0.6
Queue time during production 0
Total throughput time 1.6 days
Manufacturing cycle efficiency (MCE): Process time ÷ Throughput time 43.75%
b)
Month 6 th
Throughput time in days:
Process time 0.7
Inspection time 0
Move time 0.6
Queue time during production 0
Total throughput time 1.3 days
Manufacturing cycle efficiency (MCE): Process time ÷ Throughput time 53.85%
Add a comment
Know the answer?
Add Answer to:
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month نية Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1. 4. ? 3 ? > Throughput time...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...

  • DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible...

    DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountere relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency...

  • DataSpan, Inc. automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Throughout te (days) Delivery cycle time (days) Manufacturing cycle...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT