This problem involves doing the cross over calculations like the example on top of page 287 12th edition L07.2 or page 277 9th edition. (L02). You do not have to draw the charts as illustrated in figure 7.3.
For question 1, you can multiply and get the solution. I got this correct
For question 2, you can solve this problem by multiplying each option which is a longer process of solving it. Do not use this process. The intent of this exercise is for your to use the easier, short process of cross over analysis. If you use the longer process, you will receive a zero and ask to submit again.
For question 3, use the analysis you completed in question 2 to answer the question. No additional calculations are required.
I already got number 1 correct. not sure how to do crossover method for 2 and 3
Problem 7:1
Tanner’s Machine Shop, Inc., has a 1-year contract for the production of 350,000 gear housings for a new off-road vehicle. Owner, Danny Tanner, has developed costs for three manufacturing alternatives. They are manufacturing using general-purpose equipment (GPE), a flexible manufacturing system (FMS), and an expensive, but efficient, dedicated machine (DM). The cost data follow:
general-purpose equipment (GPE) |
flexible manufacturing system (FMS) |
dedicated machine (DM) |
|
Annual contracted units |
350,000 |
350,000 |
350,000 |
Annual fixed cost |
$100,000 |
$250,000 |
$550,000 |
Per unit variable cost |
$15.00 |
$12.00 |
$10.00 |
Contract of production Q = 3,50,000
Total cost = Fixed cost + Unit variable cost*Quantity
GPE total cost = 100000 + 15Q
FMS total cost = 250000 + 12Q
DM total cost = 550000 + 10Q
Best Contract:
Q = 3,50,000
GPE total cost = 100000 + 15*350000 = 53,50,000
FMS total cost = 250000+12*350000 = 44,50,000
DM total cost = 550000 + 10*350000 = 40,50,000
Total cost is less for DM. So best process for this contract is DM
Economical volume for each process:
Cross over point is the point where total costs will be equal
GPE total cost = FMS total cost
100000 + 15Q = 250000 + 12Q
3Q= 150000
Q = 50,000 units
FMS total cost = DM total cost
250000 + 12Q = 550000 + 10*Q
2Q = 300000
Q = 1,50,000
From this we can say
GPE is more economical when the production quantity is below 50000 units
FMS is more economical when the production quantity is within the range of 50,000 and 1,50,000
DM is more economical when production quantity is above 1,50,000 units
From the above we can say,
If Q = 40000, the best process is GPE
If Q = 55000 the best process is FMS
If Q = 100,000 the best process is FMS
This problem involves doing the cross over calculations like the example on top of page 287...
Meile Machine Shop, Inc., has a 1-year contract for the production of 250,000 gear housings for a new off-road vehicle. Owner Larry Meile hopes the contract will be extended and the volume increased next year. Meile has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS) LOADING... , and expensive, but efficient, dedicated machine (DM). The cost data follow: General-Purpose Equipment (GPE) Flexible Manufacturing System (FMS) Dedicated Machine (DM) Annual contracted units 250,000 250,000 250,000 ...
Can someone please help? Borges Machine Shop, Inc., has a 1-year contract for the production of 250,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 250,000...
Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow. Annual contracted units Annual foxed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $15.00 Flexible Manufacturing...
Borges Machine Shop, Inc., has a 1-year contract for the production of 250,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: General-Purpose Equipment (GPE) Flexible Manufacturing System (FMS) Dedicated Machine (DM) Annual contracted units 250,000 250,000 250,000 Annual...
Borges Machine Shop, Inc., has a 1-year contract for the production of 200,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: GPE FMS DM Annual Contracted Units $200,000 $200,000 $200,000 Annual Fixed Cost $100,000 $200,000 $500,000 Per unit variable...
Borges Machine Shop, Inc., has a 1-year contract for the production of 225.000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DML The cost data follow: Annual contracted units Annual fixed cost Per unit variable cost General Purpose Equipment (GPE) 225,000 $150,000 $18.00 Flexible...
Borges Machine Shop, Inc., has a 1-year contract for the production of 200 comma 000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: General-Purpose Equipment (GPE) Flexible Manufacturing System (FMS) Dedicated Machine (DM) Annual contracted units 200 comma 000 ...
Borges Machine Shop, Inc., has a 1-year contract for the production of 225 comma 000225,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They aregeneral-purpose equipment (GPE), flexible manufacturing system(FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: General-Purpose Equipment (GPE) Flexible Manufacturing System (FMS) Dedicated Machine (DM) Annual contracted units 225 comma 000225,000 225...
Borges Machine Shop, Inc., has a 1-year contract for the production of 200,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: General-Purpose Equipment (GPE) Flexible Manufacturing System (FMS) Dedicated Machine (DM) Annual contracted units 200 comma 000200,000 200...
Juryo mume Hop, Inc. has a 1-year contract for the production of 200,000 gear housings for a new off-road vehicle. Owner Luis Bor extended and the volume increased next year Borges has developed costs for three alternatives. They are general-purpose equipment (G system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow Annual contracted units Annual foxed cost Per unit variable cost General Purpose Equipment (GPE) 200.000 $150,000 $15.00 Flexible Manufacturing System (FMS) 200,000 $225,000 $14.00 Dedicated...