Question

Develop a WBS for a project in which you are going to build a bicycle. Try...

Develop a WBS for a project in which you are going to build a bicycle. Try to identify all of the major components and provide three levels of detail. Your text has great examples of how to develop a WBS.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project: Bicycle manufacturing.

Below are the set of activities involved in bicycle manufacturing. WBS should cover the various operations involved in bicycle build. Bicycle has different sub units such as Frameset, Crank set, Wheels, the breaking system, Shifting system, integration and the overall project management which monitor the progress of the activities and meeting the demand , proposed budget and timeline etc.

The sub level task for each activity contribute to complete the entire task. For eg: Frame set comprises of frame bar, handle bar and seat.

Add a comment
Know the answer?
Add Answer to:
Develop a WBS for a project in which you are going to build a bicycle. Try...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please could you solve this question? QUESTION 2 Using your own example, develop a WBS for...

    Please could you solve this question? QUESTION 2 Using your own example, develop a WBS for a project in which you are going to build a agriculture equipment. Identify all of the major components and provide three levels of detail with the identification number (10 marks) With reference to the above project Project risks can/cannot be eliminated if the project is carefully planned. Explain (4 marks) The chances of risk events occurring and their respective costs increasing change over the...

  • Please could you solve this question? QUESTION 2 Using your own example, develop a WBS for...

    Please could you solve this question? QUESTION 2 Using your own example, develop a WBS for a project in which you are going to build a agriculture equipment. Identify all of the major components and provide three levels of detail with the identification number (10 marks) With reference to the above project Project risks can/cannot be eliminated if the project is carefully planned. Explain (4 marks) The chances of risk events occurring and their respective costs increasing change over the...

  • Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views...

    Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views on the following: What is scope planning and scope creeping? What are some of the ways to avoid problems and manage scope correctly? You've been assigned the project of setting up a LAN with a broadband connection in your office. You need to provide internet connectivity for web browsing to all users. All the computers have Microsoft Windows 7 software installed. Based on your...

  • How do you develop the project plan in line with the project parameters? Ensure you cover in your...

    How do you develop the project plan in line with the project parameters? Ensure you cover in your explanation parameters such as inclusions, cost break down, timelines, assigning of roles and responsibilities including WBS and RAM as a minimum. (simple and original answer please, no hand-writing thx)

  • This week, you will start a course project. For this project, you will design and develop...

    This week, you will start a course project. For this project, you will design and develop a small website for a travel company. You will develop this website across the span of the course, building new project components each week, until you have a live, hosted website at the end of the course. This project is designed to replicate real-life situations where the clients provide only a few of their requirements and expect a prototype to be developed. Scenario Express...

  • In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software applicatio...

    In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software application that you have selected. Prepare the WBS, and submit the file to your instructor. This assignment is due Sunday at 11:59 p.m. All assignments should be uploaded in the Assignment area. Project Software Options There are many project management software applications that are designed to help develop project plans and schedules as well as keeping track of these plans and creating...

  • Consider Assignment 2 for Foundations of Project Management as a project. You need to ensure that...

    Consider Assignment 2 for Foundations of Project Management as a project. You need to ensure that you understand the requirements of the assignment, liaise with your lecturer/tutor to ensure that your understanding is accurate, and craft a high quality assignment that meets the assessment needs documented in the rubric. Considering your assignment as a project and using PMBOK: (1) Develop a work break down (WBS) structure to show the key activities required to complete Assignment 2. (2) Use the WBS...

  • Assignment #2 is to provide a problem statement, WBS diagram, activity listing, and precedence diagram. Deliverables...

    Assignment #2 is to provide a problem statement, WBS diagram, activity listing, and precedence diagram. Deliverables for HW2 shall include: · A Project Statement For the attached example (see item 3 below), the Project Statement is: “Owner to design and build a new residence. Hiring and oversight of architectural, design, and construction professionals will be managed by the Owner. All materials and permits will be provided by the Owner.” · An Activity Listing The activity listing should be prepared and...

  • Using Java In this project, you are going to build a max-heap. You will use an...

    Using Java In this project, you are going to build a max-heap. You will use an array to implement the heap. Your program should: ? Allow the user to select one of the following two choices (Note that your program needs to implement both choices): o (1) test your program with 100 randomly generated integers (no duplicates, positive numbers with proper range); o (2) test your program with the following 100 fixed values from 1, 2, 3, ..., and 100....

  • Try to build a Simulink model to demonstrate the principle of Superposition. Your model must incl...

    Please show all steps Try to build a Simulink model to demonstrate the principle of Superposition. Your model must include: 2-Step function blocks 3-Transfer function blocks . 1- Transport Delay . 1-Sum Block (located in Math Operations) 1-Scope (3 inputs) Step l: For the Transfer Function blocks, you will create one stable, first order transfer function. This transfer function should be repeated in all the three blocks. Step 2: To design the system, connect these components in a way similar...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT